![]() ![]() TM 5-3740-214-14
STARTUP AND OPERATION SUMMARY (Continued)
g.
Shutdown Procedures.
(1) Turn the solenoid valve switch OFF.
(2) Turn the ULV aerosol generator switch OFF.
(3) Open the tank pressure drain valve.
Figure 2-40. Flushing Procedures
(4) Aim the nozzle into a bucket.
(5) Fill the flush tank with soapy water.
(6) Pressurize the flush tank.
(7) Turn the solenoid valve switch ON.
(8) Turn the ULV aerosol generator ignition switch ON.
(9) Turn the three-way valve to flush and flush for about five to ten minutes.