Installation.
Up
TM-5-6115-633-14-P Power Plant AN/MJQ-18 (NSN 6115-00-033-1398) (2) MEP-003A 10Kw 60Hz Generator Sets Manual
Next
Switch to Load Terminal Wire Replacement

ARMY TM 5-6115-633-14&P
Figure 4-11. Indicator Light and Wire Assembly Replacement.
(c) Unscrew nut (13) and internal tooth Iockwasher (14) securing indicator light housing
(15) to cover (4) and slide nut and Iockwasher off wires (12).
(d) Pull terminal (9) off each wire (12).
(3) Pull out light and wires through cover (4).
(2) Installation.
Pull terminal (9) off each indicator light wire (12).
(a)
Feed wires (12) through hole in cover (4) and fit light housing (15) in hole.
(b)
Slide nut (13) and Iockwasher (14) over both wires (12), thread onto housing (15) on
(c)
inside of cover (4) and tighten.
Crimp one temrinal (9) onto each wire (12).
(d)
Position terminal (9) of each indicator light wire (12) against underside of switch term-
(e)
inal (10). Position terminal of power cable wire(11) against terminal of indicator light
wire. Insert screw (6) up through wire terminals and switch terminal. Install star washer
(8) and nut (7) on screw and tighten against switch terminal.