Page Title: Figure 4­2. Installing Power Plant.
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 

Back
Installation
Up
TM-5-6115-633-14-P Power Plant AN/MJQ-18 (NSN 6115-00-033-1398) (2) MEP-003A 10Kw 60Hz Generator Sets Manual
Next
Ground plate

ARMY TM 5-6115-633-14&P
Figure 4­2. Installing Power Plant.
WARNING
Do not operate generator sets until power plant is properly grounded
(paragraph 4-2, b.). Serious injury or death by electrocution can result
from operating an ungrounded power plant.
CAUTION
To avoid damage to equipment, make certain of voltage, frequency, and
phase requirements of load being connected to generator sets.
(6) Refer to data plate on load terminal board cover and toTM 5-6115-585-12. Connect power plant to
system or equipment to be powered.
b. Grounding. Check that generator sets are grounded to GROUND TERMINAL stud on trailer body. Using
ground wire supplied, connect power plant to a suitable ground as described below. The following sources of a good
ground are listed in order of preference.
NOTE
As a substitute for the supplied ground wire, any copper wire of at least
No. 6 AWG may be used.
4-4
Change
2