Click here to make tpub.com your Home Page

Page Title: Table 3-2. Operator/Crew Preventive Maintenance Checks and Services (PMCS) - continued
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 

Back
Table 3-2. Operator/Crew Preventive Maintenance Checks and Services (PMCS) - continued
Up
TM-5-6115-633-14-P Power Plant AN/MJQ-18 (NSN 6115-00-033-1398) (2) MEP-003A 10Kw 60Hz Generator Sets Manual
Next
Table 3-2. Operator/Crew Preventive Maintenance Checks and Services (PMCS) - continued

ARMY TM 5-6115-633-14&P
Table 3-2. Operator/Crew Preventive Maintenance Checks and Services (PMCS) - CONT.
W ­ Weekly
M - Monthly
A - After
D ­ During
B - Before
Item to be inspected.
Procedure: check for and
Interval
Equipment is not
have repaired, filled, or
Item
ready/available if:
adjusted as needed
no.
GENERATOR SET GAGES AND
21
INSTRUMENTS ­ CONT
c.  Check that current meter (28) reading
does not exceed 100% or more than 5%
load difference between phases.
Desired voltage can-
Check that voltmeter (29) indicates
d.
not be obtained and
desired output voltage as deter-
maintained.
mined by load connections and amps-
volts transfer switch.
Oil pressure drops
Check engine oil pressure gage (30)
e.
below 20 psig.
for 20 to 45 psig indication.