Click here to make tpub.com your Home Page

Page Title: Table 3-2. Operator/Crew Preventive Maintenance Checks and Services (PMCS) - continued
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 

Back
Table 3-2. Operator/Crew Preventive Maintenance Checks and Services (PMCS)
Up
TM-5-6115-633-14-P Power Plant AN/MJQ-18 (NSN 6115-00-033-1398) (2) MEP-003A 10Kw 60Hz Generator Sets Manual
Next
Table 3-2. Operator/Crew Preventive Maintenance Checks and Services (PMCS) - continued

ARMY TM 5-6115-633-14&P
Table 3-2. Operator/Crew Preventive Maintenance Checks and Services (PMCS) ­ CONT.
D ­ During
A ­ After
B - Before
W ­ Weekly
M ­ Monthly
Item to be inspected.
Interval
Procedure: check for and
have repaired, filled, or
Equipment is not
Item
ready/available if:
adjusted as needed
no.
NOTE
Perform weekly as well as before
PMCS if:
You are the assigned operator but
have not operated the equipment
since the last weekly inspection.
You are operating the equipment
for the first time.
Generator set checks and ser-
vices in this table are described as
performed on a single generator
set. These procedures must be
performed on each of the two
generator sets that make up the
AN/MJQ-18.
1
GENERATOR SET EXTERIOR
A Class Ill lubrication
a. Check on, around, and beneath the
oil or any class fuel
generator set (1) for fuel or oil
leak is detected.
leaks.
Not properly
b. Check that generator set (1)
grounded.
grounds are properly installed,
and grounding connections are
tight.
2
FUEL GAGE
Check fuel gage (2) for sufficient fuel for
continuous operation.