TM 10-1670-280-23&P 0007 00
0007 00-2
c. No. 3 and 4 personnel will grasp any two consecutive suspension lines, one in each hand, and
vigorously shake first gore. When gore is free of debris, pass line from right hand to left hand and
grasps next consecutive suspension line in right hand. Shake out each consecutive gore until all
suspension lines are held in left hand and all gores are free of debris.
d. Once gore shaking process is completed, No. 1 and 2 personnel will slowly raise suspended canopy
higher as No. 3 and 4 personnel clear suspension lines and risers of debris and removes
entanglements when possible.
First
Gore
Suspension
Lines
Entanglement
|