OPERATION UNDER USUAL CONDITIONS
GENERAL
under normal operating conditions. Operator instructions include site requirements,
launch/retrieval of BEB, BEB operation, and bridge and raft assembly construction.
In addition, operator instructions include deployment by helicopter, bridge
anchorage using BEBs, conventional and longitudinal rafting, and other
requirements for operating the BEB.
BEB PREPARATION FOR USE
Operation of the BEB under usual conditions is described in this work package.
Operation under unusual conditions is described in WP 0037 00. Prior to operating
the BEB, the operator must perform the following:
a. Ensure field maintenance has serviced the vessel; refer to
DA Form 2404/5988-E, Equipment Inspection and Maintenance Worksheet.
b. Perform all operator/crew Before PMCS as listed in WP 0046 00, Table 1.
c. Review operating instructions prior to boat operation.
d. Review the proper hand signals for operation. Refer to Hand Signals
e. Review launch and retrieval procedures (refer to WP 0010 00 and
WP 0011 00), and the Improved Boat Cradle (IBC) operating instructions
prior to its use. Refer to TM 5-5420-277-14&P.
END OF WORK PACKAGE