Click Here to
Order this information in Print

Click Here to
Order this information on CD-ROM

Click Here to
Download this information in PDF Format

     

Click here to make tpub.com your Home Page

Equipment Estimates
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books
   

 

Back
Figure 4-13.-CAS sheet
Up
Equipment Operator Advanced - Advanced construction equipmet operators manual
Next
Chapter 5 Quarry Supervisor

(AI + Al   = AZ   = 1.85 = D  = Az) x 1.85 x Distance= Cubic yards Area of one end cross section Area of other end of cross section Constant  factor Distance  between  two  end  areas  that must  be  changed  to  a  decimal  form;  for  example, 250 feet = 2.50, 125 feet = 1,25, 75 feet = .75, and so forth To compute the equation take the area of one end section (cross section) plus the area of the other end and multiply the sum of the two areas by a constant factor of 1.85. This value should now be multiplied by the distance  between  the  two  end  areas  to  determine  the number of cubic yards. (See fig. 4-12.) Earthwork  equations  to  compute  the  volume  of concrete are outlined in chapter 7. Other areas, such as equations to compute for prime and tack costs, single- and double-surface treatments, and asphalt volumes, are outlined in chapter 8. EQUIPMENT ESTIMATES Equipment  estimates  are  used  with  production schedules  to  determine  the  construction  equipment requirements  and  constraints  for  a  construction  project. One fact that must be remembered is that the speed of the  equipment  usually  averages  between  40  to 56 percent of the posted speed limit. The primary factors responsible for the variation in the percentage of the posted  speed  limit  are  as  follows:  road  conditions,  the number  of  intersections,  the  amount  of  traffic,  and hauling distances. Other factors considered are the types of material hauled (for example, damp sand or loam is much easier to handle than clay), safety (equipment limitations),  operator  experience,  conditions  of  the equipment, work hours, and the local climate. Equipment  production  must  be  determined  so  the amount  and  type  of  equipment  may  be  selected. Equipment production rates are available in the  Seabee Planner’s and Estimator’s Handbook,  NAVFAC  P-405. The  handbook  provides  information  on  estimating construction work elements and material quantities, including  equipment  and  manpower  requirements.  The production rate per day should be estimated for each piece  of  equipment.  Consider  the  factors  discussed above, information obtained from NAVFAC P-405, and your  experience.  The  quantity  of  work  divided  by  the production  rate  per  day  produces  the  number  of  days required to perform the project. Equipment required to support each construction activity is documented on the Construction  Activity  Summary  Sheet  (CAS  sheet)  (fig. 4-13), which is part of the project package. One of the purposes  of  the  project  package  is  to  allow  the  project supervisor and the assigned P&E crew to perform a documented  thorough  analysis  of  their  assigned  project and to lay out an organized sequence plan of operation in order to complete the assigned tasking. Detailed information  on  project  packages,  project  planning, project  execution,  and  construction  project  supervision are outlined in the Naval  Mobile  Construction  Battalion Crew  Leader’s  Handbook. 4-11

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing