![]() ![]() TB 11-6625-2715-50
SECTION III
PRELIMINARY PROCEDURE
1-7. Preliminary Instructions. a. Hold TI so that the
b. Check TI for mechanical zero and adjust if
meter is in a horizontal position and move slightly to the
necessary.
right and left and observe that the pointer swings freely.
1-8. Equipment Setup. Connect equipment as shown
in figure 1.
Figure 1. Ammeter Current Calibration, EL 6625-2715-50-TB-1 equipment setup.