Back REPLACE INTAKE BAFFLE ASSEMBLY | Up TM-5-6115-634-14P Power Plant AN/MJQ-16 (NSN 6115-00-033-1395) (2) MEP-002A 5 Kw 60 Hz Generator Sets M103A3 2-Wheel 2-Tire Modified Trailer Manual | Next REPLACE GRID |
TM5-6115-634-14&P
NAVFAC P-8-647-14&P
T0-35C2-3-445-14
TM-6115-14&P/1
4-14. REPLACE INTAKE BAFFLE ASSEMBLY (cont)
INSTALLATION
INSTALL INTAKE BAFFLE ASSEMBLY.
a.
b.
c.
d.
Position intake baffle assembly
and align the screw holes.
Install one top screw (1),
and flatwasher (2) on each
side.
Install remaining 10 screws
(1), and flatwashers (2), top,
right, left, and bottom of
intake baffle assembly.
Tighten 12 screws.
4-16
|