Order this information in Print

Order this information on CD-ROM

Download in PDF Format

     

Click here to make tpub.com your Home Page

Page Title: Table 4-2. PU 794/G, TROUBLESHOOTING PROCEDURES
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books
   

 

Back
Table 4-2. PU 794/G, TROUBLESHOOTING PROCEDURES
Up
TM-5-6115-634-14P Power Plant AN/MJQ-16 (NSN 6115-00-033-1395) (2) MEP-002A 5 Kw 60 Hz Generator Sets M103A3 2-Wheel 2-Tire Modified Trailer Manual
Next
REPLACE BATTERY

TM5-6115-634-14&P NAVFAC  P-8-647-14&P T0-35C2-3-445-14 TM-6115-14&P/1 Table 4-2. PU 794/6, TROUBLESHOOTING PROCEDURES (CONT) MALFUNCTION TEST OR INSPECTION CORRECTIVE ACTION 2. APPROPRIATE INDICATOR LAMP DOES NOT ILLUMINATE AT REMOTE CONTROL UNIT. Step 1. Check indicator lamp for open filament. Replace lamp if filament is open. Step 2. Refer to FO-2 and test control cables and junction box for continuity in indicator lamp circuit. Replace faulty cable or junction box. Step 3. Test remote control unit. Replace faulty remote control unit. Step 4. If indicator lamp still does not illuminate, remote functions box assembly is faulty. Report to intermediate direct support Section  IV. MAINTENANCE  PROCEDURES maintenance. 4-9. General Instructions PU 794/G. Each maintenance function will be performed with the PU 794/G shut This section provides organizational down and negative battery cable discon- maintenance instructions for the nected, except where otherwise stated. 4-7