Order this information in Print

Order this information on CD-ROM

Download in PDF Format

     

Click here to make tpub.com your Home Page

Page Title: Single Unit Operating Procedures
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books
   

 

Back
Figure  2-5. Cable Connection for Two PU 794/G’s
Up
TM-5-6115-634-14P Power Plant AN/MJQ-16 (NSN 6115-00-033-1395) (2) MEP-002A 5 Kw 60 Hz Generator Sets M103A3 2-Wheel 2-Tire Modified Trailer Manual
Next
Preparation  for  Movement

TM5-6115-634-14&P NAVFAC  P-8-647-14&P T0-35C2-3-445-14 TM-6115-14&P/1 2-5. Single Unit Operating Procedures a. Starting the PU 794/G From the Remote Control Unit (1)  Perform  before  operation  PMCS. (2) Ensure the PU 794/G has been cabled for single unit operation accord- ing to paragraph 2-3.b. (3) Using the remote control unit for SET No. 1 (Figure 2-2), place the ENGINE switch in the START position and hold until the ENG RUNNING light is illuminated for five seconds. Release the  switch. NOTE If the ENG RUNNING light does not illuminate in 15 seconds, place the ENGINE switch in the STOP position. Wait at least 15 seconds before attempting to start again. Attempt to two more times. If the unit fails to start, refer to troubleshooting  procedures. NOTE When the PARALLEL OPERATION/ SINGLE UNIT OPERATION switch is in the PARALLEL OPERATION position, hold the BATTLE SHORT switch in the ON position until the CONTACTOR CLOSED light illuminates. (4) Hold the CONTACTOR switch in the CLOSE position until the CONTACTOR CLOSED light illuminates. Release the switch. (5) Frequency can be adjusted by using the FREQ ADJUST control on the remote control unit while another person is watching the frequency meter on the power  unit. b. Stopping the PU 794/G From the Remote  Control  Unit. (1) Place the CONTACTOR switch in the OPEN position. (2) Allow the PU 794/G to operate for 3 minutes with no load applied. (3) Place the ENGINE switch in the STOP position. (4)  Perform  after  operation  PMCS. c. Starting-Operating-Stopping PU 794/U From the Generator Set  Controls. Hearing protection is required when working in the area of the PU 794/G when engine is running with access doors open. Failure to do so could result in  hearing  loss. (1)  Perform  before  operation  PMCS. (2) Ensure PU 794/G has been cabled for single unit operation according to paragraph  2-3.b. (3) Remove one end of the 5-foot (1.52 meters) control cable from the control connector on the connector plate. (4) Remove the shorting plug from the storage shorting-connector on the connector place. (5) Connect the shorting plug in the control connector on the connector plate. (6) Refer to the operating plate located on the inside of the generator control right door panel for starting- operating-stopping the PU 794/G. (7) After stopping generator, remove shorting plug from the control connector of the connector plate. (8) Install shorting plug in the storage shorting-connector on the con- nector  plate. (9) Install free end of 5-foot (1.52 meters) control cable in the con- trol connector of the connector plate. 2-16