Order this information in Print

Order this information on CD-ROM

Download in PDF Format

     

Click here to make tpub.com your Home Page

Page Title: Figure 6-7. AC Output Control Box Test Setup
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books
   

 

Back
Figure 6-5.1. AC Voltage Regulator Schematic
Up
TM-5-6115-585-34 Generator Set Diesel Engine Driven Tactical Skid Mtd 5 KW 1 Phase 2 Wire 1 Phase-3 Wire 3 Phase-4 Wire 120 120/240 and 120/208 Volts Manual
Next
Table  6-5.  Reconnection  Switch  Continuity

Figure  6-7.  AC  Output  Control  Box  Test  Setup (12)   Output-Control   Box   Housing   (24,   figure   6-9). Inspect   output   control   box   housing   for   physical   damage. Check  that  all  hingeq  covers,  and  latches  operate  properly. Check   that   all   nameplates   are   in   place.   Check   that   side access  cover  is  alwavs  in  date  when  box  is  being   actively serviced. b.  Test. (1)  Reconnection  Switch  (S6)  (1,  figure  6-10).  Tag and   disconnect   electrical   connections   except   jumper   wires from   reconnection   switch.   Using   an   ohmmeter   check   for continuity   between   terminals   listed   in   table   6-5   for   each of  the  three  switch  positions.  If  continuity  is  not  found  for each   pair   of   terminals   listed,   replace   reconnection   switch. If  continuity  is  found  between  any  other  terminals  switch should  be  replaced. (2)  AC  Circuit  Breaker  (CB1).  Test  that  breaker  will remain  in  both  the  ON  and  OFF  positiona. (3)  15  Amp  Circuit  Breaker  (CB3).  Test  that  breaker will  remain  in  both  the  set  (pushed)  and  tripped  (pulled) positions. (4)   Convenience   Receptacle   (J14).   With   15   amp circuit   breaker   in   proper   operating   position,   test   con- venience   receptacle   using   a   120   volt   trouble   light   or voltmeter. With   the   unit   operating   and   the   15   amp circuit   breaker   pushed   in,   120   volts   should   be   present at the receptacle. (5)   Linear   Reactor   (Ll).   Disconnect   electrical connectors   from   control   box.   Use   an   ohmmeter   to   check TM5-6115-585-34 NAVFAC    P-8-623-34 TO-35C2-3-455-2 TM-05684C/05685B-34 resistance  of  each  of  the  three  windings  in  the  reactor by  checking  resistance  between  terminals  1  and  2,  3  and 4,  5  and  6.  Resistance  for  each  winding  must  be  13.5  ohms plus  or  minus  1.35,  if  not  replace  reactor. (6)   Connector   Assemblies.   Test   for   continuity between  each  pin  and  case  for  shorts  to  ground. (7)   Current   Voltage   Transformer   (CVT1).   Using   an ohmmeter  check  three  primary  windings  of  transformer (figure  1-1,  6-7.1  and  6,  figure  6-9)  by  measuring  resistance from  terminals  H1  to  H2,  H3  to  H4,  H5  to  H6.  Resistance must  be  2.27  ohms  ±  0.227  ohms.  Check  resistance  in  three secondary   windings   of   transformer   by   checking   from terminals   Xl   to   X2,   Xl   to   X3,   X2   to   X3.   Resistance must   be   1.68   ohms   ±   0.168   ohms.   Check   resistance   in control   windings   by   checking   from   terminals   Cl   to   C2. Resistance  must  be  9.6  ohms  ±  0.96  ohms.  If  any  of  the windings   do   not   show   the   proper   resistance,   replace transformer. (8)   Current   Transformer   (CT1).   On   the   current transformer  (figures  1-1,  6-7.1  and  7,  figure  6-9)  only  the secondary   windings   can   be   checked.   Using   an   ohmmeter check   resistance   in   secondary   windings   by   checking   from terminals  1A  to  2A,  lB  to  2B,  lC  to  2C.  Resistance  must be  0.5  ohms  ±  0.05  ohms.  If  any  of  the  windings  do  not show  the  proper  resistance,  replace  transformer. (9)  Bridge  Rectifier  Assembly  (A4)  (see  figure  6-11). Tag  and  remove  leads  to  terminal  board  and  test  each diode   (3)   separately   by   checking   between   terminals   (6) shown  in  table  6-6.  Resistance  in  one  direction  should  be very   high   in   one   direction   and   very   low   in   the   other. Measure  resistance  of  R1  (4).  It  should  be  56  ohms. Change 5 6-15