TM 5-3810-306-34
d Cover opening to prevent dirt from getting
into pump drive opening.
INSTALLATION:
NOTE
If pump is being installed on new
torque converter, it will be necessary
to install new studs in pump drive
flanges. Using a prick punch, peen
studs at mounting flange holes.
1 INSTALL TWO-SECTION HYDRAULIC PUMP
(4).
a Uncover pump opening.
b If removed, install pump drive sleeve.
c Install a new gasket (3) between pump (4)
and pump drive coupling. Apply silicone
sealant to gasket.
d Install the pump (4) using nuts (1) and
NOTE
Coat new preformed packings with
CAUTION
clean hydraulic oil prior to assembly.
Hot oil must not be fed into a cold
e Connect hydraulic hoses (9) with new
pump. It may cause pump to seize.
preformed packing (8) to pump as tagged
during removal using split flanges (7),
4 DRAIN AND FLUSH HYDRAULIC SYSTEM.
2 INSTALL TORQUE CONVERTER CHARGING
5 BLEED AIR FROM HYDRAULIC SYSTEM.
(REFER TO PAGE 13117.) OBSERVE FOR
LEAKS AND PROPER OPERATION.
3 CONNECT NEGATIVE BATTERY CABLE AT
SHUNT. (REFER TO TM 5-3810-306-20.)
6 INSTALL REAR DECKING. (REFER TO TM 5-
3810-306-20.)
7.
INSTALL ENGINE TOP
COVER. (REFER TO TM 5-3810-306-20.)
END OF TASK
13-25