| |
Back Sizing Sanitary Collecting Sewers | Up Utilitiesman (Advanced) - Manual for electric, plumbing, water and other utilities | Next Table 7-6.—Minimum Slope for Sewer Pipe |
Table 7-6.Minimum Slope for Sewer Pipe
on the same grade. Therefore, an increase in pipe
size to obtain the desired flow velocity is limited
by the rate of flow. Typical minimum flow
velocities are 2 feet per second when the design
flow fills the pipe and 1.6 feet per second at the
average rate of flow. Maximum velocities must
also be considered; too high a velocity will erode
the pipe. A typical maximum velocity is 15 feet
per second for concrete pipe. Because of the
differences in available slopes, smaller pipe may
be used in some sections than is required in an
upper section of the same sewer. The pipe size
should be reduced whenever better flow condi-
tions would result.
Manholes provide access to sewers for inspec-
tion and cleaning. They are placed where there
is a change in grade, a change in pipe size, a junc-
tion of two or more sewerlines, or a change in
direction. Otherwise, they are placed at intervals
of 300 or 500 feet of sewerline. The manholes
should be built so there is no decrease in velocity
and a minimum of water disturbance. The channel
should be deep enough to prevent sewage from
spreading over the manhole bottom. The covers
should be of a weight strong enough to support
the expected traffic. Perforated covers should not
be used for sanitary sewer manholes, because
openings in the sewer manhole would permit the
entrance of sand, grit, and surface water. The
sewers are ventilated by the stacks of the building
plumbing systems.
STORM DRAINAGE SYSTEMS
Storm drainage systems should be separate
from sanitary sewage systems wherever possible.
Some Navy bases may have combination systems
still in use. However, storm water should never
be drained into sewers intended for sanitary
sewage only.
EOs and BUs generally are responsible for
building ditches, culverts, and other structures
that are a part of storm sewers. Therefore, con-
struction of these facilities is not covered in this
chapter.
The UT is generally concerned with only the
pipework itself. This involves laying storm drain
lines both inside and outside buildings and other
structures. This pipe material may be the same
as that used for the sanitary system. Storm sewer
systems, however, may include pipe of much
larger sizes than are needed for sanitary sewers.
Plain or reinforced concrete pipe (rather than clay,
cast iron, or asbestos cement) is generally used
for the larger lines. Also, it is not so important
that the joints be watertight in storm sewer
systems. In fact, the mortar is sometimes
omitted from a portion of the joint and washed
gravel is placed next to the opening; the storm
drain thus serves also as an underdrain to pick
up subsurface water.
Installation Considerations
Storm and sanitary systems may differ in the
installation of the piping. Building storm drains
should generally be graded at least 1/4 inch per
foot whenever feasible. This amount of drop per
foot provides an unobstructed and self-scouring
flow. However, a greater drop per foot may be
given as no fixture traps which might lose their
seals are associated with it.
When a change of direction is necessary, long
radius fittings are used and a cleanout need not
be installed. This is especially true in and under
buildings. But a manhole is used outside of
buildings when a change of direction is necessary,
or when two or more lines are connected together.
Storm drainage systems are designed to drain
all surface and sometimes subsurface water that
Sizing Building Storm Drains
may cause damage to Navy facilities, property,
or adjoining land. They consist of pipe, inlets,
To determine the size of building storm drains,
catch basins, and other drainage structures to
a number of factors must be considered, such as
carry the surface runoff and subsurface water to
rainfall intensity, roof size, and pitch of roof.
a point of disposal.
Tables have been made for use in estimating the
7-9
|