4. Place the meter probes across a load. If there is no-voltage reading, you have an
inoperative load. Replace the load.
Place one meter probe on the right
side of the LLP switch and the other probe
on the left side of the IT. If there is no
voltage reading, replace the load.
Continuity Readings
To perform an ohmmeter continuity test, set your multimeter to resistance; disconnect the
power and remove the wires from the component being tested. Perform a continuity test as
follows:
1. Place the meter probes across a path. If a reading is obtained, it indicates an open path.
Place one meter probe on the left side
of the CR contact and the other probe on the
left side of the HP switch. If you obtain a
reading, the path is open.
2. Place the meter probes across a path. If a zero reading is obtained, the path is closed.
Place one meter probe on the left side
of the CR contact and the other probe on the
left side of the HP switch. With the CR
contact closed, you should obtain a zero
reading. This indicates the path is closed.