| |
Back Hazardous Materials Storage | Up Steelworker Volume 02 - Building manual for how to work with steel | Next Construction Drawings |
Activity Estimates
An activity estimate is a listing of all the steps
required to construct a given project, including
specific descriptions as to the limits of each clearly
definable quantity of work (activity). Activity
quantities provide the basis for preparing the material,
equipment, and manpower estimates. They are used to
provide the basis for scheduling material deliveries,
equipment, and manpower. Because activity estimates
are used to prepare other estimates and schedules,
errors in these estimates can multiply many times. Be
careful in their preparation!
Material Estimates
A material estimate consists of a listing and
description of the various materials and the quantities
required to construct a given project. Information for
preparing material estimates is obtained from the
activity estimates, drawings, and specifications. A
material estimate is sometimes referred to as a Bill of
Material (BM) or a Material Takeoff (MTO) Sheet.
Equipment Estimates
Equipment estimates are listings of the various
types of equipment, the amount of time, and the
number of pieces of equipment required to construct
a given project. Information, such as that obtained
from activity estimates, drawings, specifications, and
an inspection of the site, provides the basis for
preparing the equipment estimates.
Manpower Estimates
The manpower estimate consists of a listing of the
number of direct labor man-days required to complete
the various activities of a specific project. These
estimates will show only the man-days for each
activity, or they can be in sufficient detail to list the
number of man-days for each rating in each
activityBuilder (BU), Construction Electrician
(CE), Equipment Operator (EO), Steelworker (SW),
and Utilitiesman (UT). Man-day estimates are used in
determining the number of personnel and the ratings
required on a deployment. They also provide the basis
for scheduling manpower in relation to construction
progress.
When the Seabee Planners and Estimators
Handbook, NAVFAC P-405, is used, a man-day is a
unit of work performed by one person in one 8-hour
day or its equivalent. One man-day is equivalent to a
10-hour day when the Facilities Planning Guide,
NAVFAC P-437, is used.
Battalions set their own schedules, as needed, to
complete their assigned tasks. In general, the work
schedule of the battalion is based on an average of 55
hours per man per week. The duration of the workday
is 10 hours per day, which starts and ends at the jobsite.
This includes 9 hours for direct labor and 1 hour for
lunch.
Direct labor (Timekeeping as previously
discussed) includes all labor expended directly on
assigned construction tasks, either in the field or in the
shop, that contributes directly to the completion of the
end product. Direct labor must be reported separately
for each assigned construction item. In addition to
direct labor, the estimator must also consider overhead
labor and indirect labor. Overhead labor is considered
productive labor that does not contribute directly or
indirectly to the product. It includes all labor that must
be performed regardless of the assigned mission.
Indirect labor includes labor required to support
construction operations but does not, in itself, produce
an end product.
SCHEDULING
Scheduling is the process of determining when an
action must be taken and when material, equipment,
and manpower are required. There are four basic types
of schedules: progress, material, equipment, and
manpower.
Progress schedules coordinate all the projects of a
Seabee deployment or all the activities of a single
project. They show the sequence, the starting time, the
performance time required, and the time required for
completion.
Material schedules show when the material is
needed on the job. They can also show the sequence
in which materials should be delivered.
Equipment schedules coordinate all the
equipment to be used on a project. They also show
when it is to be used and the amount of time each piece
of equipment is required to perform the work.
Manpower schedules coordinate the manpower
requirements of a project and show the number of
personnel required for each activity. In addition, the
number of personnel of each rating (Steelworker,
Builder, Construction Electrician, Equipment
Operator, and Utilitiesman) required for each activity
for each period of time can be shown. The time unit
1-18
|