Click Here to
Order this information in Print

Click Here to
Order this information on CD-ROM

Click Here to
Download this information in PDF Format

 

Click here to make tpub.com your Home Page

Page Title: Figure 2-36.-Project transfer letter.
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books

   

 

Back
Figure 2.35.-Punchlist from ROICC.
Up
Naval Construction Force/Seabee 1&C - Construction manual for building structures
Next
Chapter 3 Construction Management

inspection. If there are no discrepancies, beneficial The transfer letter also must include a statement of occupancy  is  established  upon  completion  of  the  final actual material cost and statistical labor costs. Figure inspection and the 1-year warranty takes effect. At 2-36 is a sample of the transfer letter. If the ROICC did this time, the battalion prepares a letter to the ROICC not include 2ndNCB/3rdNCB on the distribution of advising  that  the  project  has  been  completed.  This their acceptance letter, the battalion will forward a transfer  letter  shall  include  two  sets  of  as-built  draw- copy. The ROICC acceptance letter is placed in the ings,  all  installation,  operation,  maintenance,  and  other project  files.  The  project  files  are  then  closed  and technical service manuals, including parts catalogs. retained for 2 years. Figure  2-36.-Project  transfer  letter. 2-49