make sure your project is ready. Arrange, through your
FINAL ACCEPTANCE
QC staff, for a preliminary acceptance inspection with
the ROICC. After this inspection, the battalion will take
In most cases the project will not be turned over to
the necessary actions to complete any punchlist items.
the customer until all of the punchlist items have been
The battalion will complete these items as soon as
completed. When all of the punchlist items have been
possible. The punchlist should be provided in writing
completed, the crew leader will arrange through the QC
from the ROICC following the inspection similar to
for a final inspection with the ROICC and a customer
figure 2-35.
representative. There should be no punchlist at this
Figure 2.35.-Punchlist from ROICC.