Back Project Closeout | Up Naval Construction Force/Seabee 1&C - Construction manual for building structures | Next Figure 2-34.-Pre-BOD inspection request (page 2). |
TOOL, EQUIPMENT, AND
and tool kits returned to CTR must be inventoried with
MATERIAL TURN-IN
1250-1s filled out for any missing or broken items.
Turn all material into MLO using a 1250-1 filled out
The crew leader must ensure the jobsite is clean!
in red ink with the appropriate bill of material line item
All tools, excess material, and civil engineering
number. Project material as well as tools purchased
support equipment (CESE) must be properly cleaned,
with project funds must be offered to the customer
inventoried, and returned to the proper outlet. Tools
prior to being considered excess.
Figure 2-33.Pre-BOD inspection request (page 1).
2-46
|