| |
Back Master Activity Percent Complete (WIP) | Up Naval Construction Force/Seabee 1&C - Construction manual for building structures | Next Figure 2-26. Level II barchart with progress curve |
Table 2-3.Percent Deviation
activities not started, the man-days remaining will
equal the original man-day estimate for that master
activity. For master activities under construction you
must calculate the completion status of each
individual construction activity. Construction
activities that are 100 percent complete has zero
man-days remaining. Construction that has not begun
has man-days remaining equal to the original man-day
estimate. If a construction activity with an original
estimate of 20 man-days is 25 percent complete, the
man-days remaining is 15. There are 15 man-days
remaining because 75 percent of the work is left to be
done and 75 x 20/100 equals 15.
Man-days Expended
Man-days expended have nothing to do with
percent complete and are not included in the SITREP
when it leaves the battalion. It is included on the
SITREP feeder so the company staff and the Ops
department can see where your man-days have gone.
The man-days expended may be used for insight into
why a particular project is behind. The total man-days
expended is also needed to update the level II with
actual progress and cumulative man-days expended.
Comments Lines
The SITREP feeder also has several lines for
comments. This is for the crew leaders draft input for
the SITREP. The battalion must include in its SITREP
brief comments describing work performed since the
last SITREP. Remember, if the actual WIP is less than
the scheduled WIP, the delay must be explained and a
plan for getting the project back on schedule must be
included.
SITUATION REPORT (SITREP)
With the information from your SITREP input, the
battalion can now formulate the situation report. A
message SITREP must be submitted monthly by the
battalion within 3 workdays after the last day of each
month. The report includes all tasked projects listed in
increasing numerical sequence. Once construction has
started on a project, the project is considered as active
and is not removed from the report until such time as
the project has been accepted as totally complete by
the RO1CC. Once a project has been completed, and a
UCD/BOD (usable completion date/beneficial
occupancy date) has been established, it may be
deleted from future reports.
Project Status Summary
All SITREPs include a project status summary by
location. This summary provides project WIP,
remaining project man-days, and completion date
percentage data. The status summary also contains a
brief description of the work accomplished during the
reporting period for each project. Each location must
be detailed as a separate subparagraph. For projects
for which no work was accomplished during the
reporting period, the master activities status and
activities reporting lines may be shown as no report.
However, when no work is accomplished, the reason
for a no work status must be adequately explained in
the comments lines as part of the status explanation.
Change of Usable Completion Date (UCD)
During the home port planning process,
2ndNCB/3rdNCB will discuss UCDs with the
battalion as required. This discussion ensures that
applicable information is considered when
2-35
|