Click Here to
Order this information in Print

Click Here to
Order this information on CD-ROM

Click Here to
Download this information in PDF Format

 

Click here to make tpub.com your Home Page

Page Title: Situation Report (SITREP)
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books

   

 

Back
Master Activity Percent Complete (WIP)
Up
Naval Construction Force/Seabee 1&C - Construction manual for building structures
Next
Figure 2-26. Level II barchart with progress curve

Table 2-3.—Percent Deviation activities not started, the man-days remaining will equal the original man-day estimate for that master activity.  For  master  activities  under  construction  you must  calculate  the  completion  status  of  each individual   construction   activity.   Construction activities  that  are  100  percent  complete  has  zero man-days remaining. Construction that has not begun has man-days remaining equal to the original man-day estimate. If a construction activity with an original estimate of 20 man-days is 25 percent complete, the man-days  remaining  is  15.  There  are  15  man-days remaining because 75 percent of the work is left to be done and 75 x 20/100 equals 15. Man-days Expended Man-days  expended  have  nothing  to  do  with percent  complete  and  are  not  included  in  the  SITREP when  it  leaves  the  battalion.  It  is  included  on  the SITREP  feeder  so  the  company  staff  and  the  Ops department  can  see  where  your  man-days  have  gone. The man-days expended may be used for insight into why a particular project is behind. The total man-days expended is also needed to update the level II with actual  progress  and  cumulative  man-days  expended. Comments Lines The  SITREP  feeder  also  has  several  lines  for comments. This is for the crew leader’s draft input for the SITREP. The battalion must include in its SITREP brief comments describing work performed since the last SITREP. Remember, if the actual WIP is less than the scheduled WIP, the delay must be explained and a plan  for  getting  the  project  back  on  schedule  must  be included. SITUATION REPORT (SITREP) With the information from your SITREP input, the battalion can now formulate the situation report. A message SITREP must be submitted monthly by the battalion within 3 workdays after the last day of each month. The report includes all tasked projects listed in increasing  numerical  sequence.  Once  construction  has started on a project, the project is considered as active and is not removed from the report until such time as the project has been accepted as totally complete by the RO1CC. Once a project has been completed, and a UCD/BOD   (usable   completion   date/beneficial occupancy  date)  has  been  established,  it  may  be deleted  from  future  reports. Project Status Summary All SITREPs include a project status summary by location.   This   summary   provides   project   WIP, remaining  project  man-days,  and  completion  date percentage  data.  The  status  summary  also  contains  a brief  description  of  the  work  accomplished  during  the reporting period for each project. Each location must be detailed as a separate subparagraph. For projects for  which  no  work  was  accomplished  during  the reporting  period,  the  master  activities  status  and activities reporting lines may be shown as no report. However, when no work is accomplished, the reason for a no work status must be adequately explained in the comments lines as part of the status explanation. Change of Usable Completion Date (UCD) During   the   home   port   planning   process, 2ndNCB/3rdNCB  will  discuss  UCDs  with  the battalion  as  required.  This  discussion  ensures  that applicable   information   is   considered   when 2-35

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing