Click Here to
Order this information in Print

Click Here to
Order this information on CD-ROM

Click Here to
Download this information in PDF Format

 

Click here to make tpub.com your Home Page

Page Title: Master Activity Percent Complete (WIP)
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books

   

 

Back
Figure 2-25.—SITREP feeder example.
Up
Naval Construction Force/Seabee 1&C - Construction manual for building structures
Next
Situation Report (SITREP)

man-day estimate was 29. When 29 is divided by 434 the  answer  is  0.07  weighted  percent. Master Activity Percent Complete (WIP) Obviously,  for  master  activities  not  started  the WIP  is  zero  percent  and  for  completed  master activities the WIP is 100 percent. For master activities that are partially complete, the crew leader must look at  the  status  of  the  individual  construction  activities. Table  2-2  is  expanded  from  figure  2-25  for  master activity 30, foundation/slab. In evaluating the progress on master activity 30 you can see that you have completed the prefab of the forms  and  the  RST.  These  construction  activities represent 17 and 20 percent of the master activity. For the set forms/RST activity you obtained the 50 percent complete   by   actual   measurement.   Do  not  use man-days expended, for they have nothing to do with WIP. In this case you measured and determined that one-half of the forms and RST have already been set. Set forms/RST represents 40 percent of the master activity, since you are half done you get credit for 20 percent.  Add  the  20  percent  plus  the  previous  17 percent  and  20  percent  for  a  total  of  57  percent completion for master activity 30. Project  Percent  Complete Project  percent  complete  represents  that  por- tion  of  the  work  completed  on  the  master  activity that  contributes  to  the  overall  project  comple- tion.   You   get   the   project   percent   complete   by multiplying  the  weighted  percent  by  the  master activity  percent  complete  (WIP)  for  each  activity. Look  at  figure  2-25  master  activity  20,  underslab utilities. The project percent complete was determined by multiplying the weighted percent of 0.07 times the percent WIP of 80 to get a project percent complete of 5.6 (0.07 x 80 = 5.6). Actual Percent Complete Actual percent complete for the project is the total of the project 90 complete column. For the example in figure 2-25 the actual percent complete for this project is  14.2  percent.  You  will  need  to  record  the  scheduled percent  complete  at  the  bottom  of  the  SITREP  feeder. You  need  to  compare  the  actual  progress  to  the scheduled progress. The scheduled percent complete comes  from  either  the  Deployment  Execution  Plan (within  the  first  45  days  of  the  deployment)  or  the Revised  Deployment  Execution  Plan  (after  the  45-day review).  The  allowable  percent  deviation  between actual WIP and scheduled WIP is shown in table 2-3. If the actual WIP is less than the scheduled WIP by more than the percentage shown in table 2-3, the battalion must advise 2ndNCB/3rdNCB by message. This message must contain a plan detailing how to get the project back on track. It must also request approval for any required changes to the battalion level I or the project level II in the revised deployment execution plan. Man-days  Remaining Man-days  remaining  area  reflection  of  how  much work remains to be done on the project.  Man-days remaining has nothing whatsoever to do with how many man-days have been expended.  For  master activities that are complete (see master activity 10, fig. 2-25) the man-days remaining are zero. For master Table 2-2.—Master Activity Percent Complete 2-34

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing