SITREP INPUT
The battalion sends to 2ndNCB/3rdNCB monthly
SITREPs that report on the progress of construction
tasking. The accuracy of the SITREPs is a reflection
of how well the crew leaders have documented labor
expended on the projects (timecards) and the quality
of the input provided by the crew leaders and the
companies. Figure 2-25 is an example of a SITREP
feeder with information, calculations, and totals
designed to help you create accurate reports.
Weighted Percent
The weighted percent for each master activity in
figure 2-25 is simply the man-days estimated for that
master activity divided by the total project man-days
estimated. For master activity 60, rough utilities, the
Figure 2-25.SITREP feeder example.