| |
Back Level II Barchart | Up Naval Construction Force/Seabee 1&C - Construction manual for building structures | Next Figure 2-21.—Level III barchart showing biweekly project status. |
expressed as a percent (multiplied by 100). If you look
back at the level III barchart, you will see that master
activity 10 has 10 man-days scheduled during the
week beginning 18 May, and 9 man-days scheduled
during the week beginning 25 May. Figure 2-20 has a
horizontal bar connecting the weeks of 18 and 25 May
for master activity 10 (sitework). The scheduled
man-days for activity 10 are printed above the bar.
Once you have all the bars signifying master
activity durations and the man-days scheduled on the
barchart, you total the man-days scheduled for each
2-week period at the bottom of each column. The
cumulative man-days scheduled is equal to the
man-days scheduled for each 2-week period added to
all previous man-days scheduled. The percent
complete scheduled (plot) is equal to the cumulative
man-days scheduled divided by the total project
man-days. The scheduled progress curve is then
drawn by plotting the percent complete scheduled at
the end of each 2-week period plotted against the
percentage scale on the right of the level II barchart.
PROJECT EXECUTION
Satisfactory execution of construction tasking
requires that various resources come together at a
specific time and place. It is not just materials,
equipment, and personnel. It is the correct materials,
the proper equipment, and capable personnel. Your
job of managing construction projects is made much
simpler if you have already identified what you need
to complete each activity. During the project planning
stage, you identified the tools, equipment, materials,
and personnel required for each part of the
construction activity. This section of the chapter
explains the various methods you can use to track
these resource requirements from the home port
planning phase to the day you begin work and
eventually close out the project.
date on the CAS sheet and circle it in yellow. Of
particular significance are the local purchase
materials. In general, no local purchase material is
procured until requested by the crew leader. This
request may be in the form of a 45-day material plan
completed by the crew leader while in home port or a
1250-1 turned into MLO several weeks in advance. It
is the crew leader who must initiate the local purchase
action. Lead times for obtaining equipment and
materials vary from several days for materials in the
MLO yard to several weeks for equipment rented
from a private contractor. If MLO needs a lead time of
2 weeks for a concrete request and you have a
concrete placement scheduled for 30 September,
make a note on the CAS sheet to turn in a 1250-1 by
16 September.
LEVEL III BARCHARTS
An accurate assessment of the project status must
be maintained on the jobsite continuously. Even a
single days deviation from your schedule makes a big
difference to the concrete supplier, the hired crane
operator, and your subcontractors. This does not mean
that your project has to be replanned every 2 weeks.
Updated project status can be reflected on the posted
level III barchart. The critical path should be
highlighted in red. The daily status should be shown
in yellow. Daily status will show where you stand on
each activity in comparison to the schedule. Figure
2-21 demonstrates a technique for reflecting total
project status on a biweekly basis. Two vertical lines
are drawn on the barchart, one at the 15th and one at
the 30th of each month. The line on the 15th is broken
and the line on the 30th is solid. Depending on the
date, the line shows at a glance which activities are
ahead or behind. Refer to figure 2-21; notice that
activities 101 and 102 were completed by the 15th.
Also notice that activity 401 is 1 day ahead and
activity 402 is 1 day behind. By the 30th all scheduled
work will be completed.
CAS SHEETS
TWO WEEK SCHEDULES
Proper use of CAS sheets greatly reduces the
chance of the construction effort being slowed or
halted due to a lack of resources. The majority of the
resource requirements identified on the CAS sheet
require some further action on the part of the crew
leader. Any action required can be tracked right on the
CAS sheet. Highlight the required action whether it is
a requisition to be submitted or an equipment request
to be turned in. List the required action and the due
A successful crew leader must manage a project
on three different planes. The crew leader must
directly supervise the construction effort underway.
The crew leader must also look at activities scheduled
for the next 2 weeks to ensure an uninterrupted flow
of resources to the project. And he/she must keep an
eye on any long lead items. It is the long lead items
that, if not tracked continuously, would be most likely
2-26
|