Click Here to
Order this information in Print

Click Here to
Order this information on CD-ROM

Click Here to
Download this information in PDF Format

 

Click here to make tpub.com your Home Page

Page Title: Level II Barchart
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books

   

 

Back
Figure  2-19.—-Level  III  barchart  sorted  by  activity  number.
Up
Naval Construction Force/Seabee 1&C - Construction manual for building structures
Next
Project Execution

never backward. Also remember that activities that show  no  free  float  are  tied  by  dependency  to  other activities. If one moves the others must move. Such is the case of activities 4000 and 4005. Some  minor  adjustments  on  crew  sizes  and durations  may  be  required  to  ensure  full  use  of assigned crew. Once all the activities are scheduled, you can input the noncritical resources and delayed start dates (using lags) and create a new barchart. You can  create  this  new  barchart  with  the  computer  or manually. LEVEL II BARCHART You make a level II barchart from the information gained from the level III. Figure 2-19 is a level III barchart with construction activities sorted by activity number. This sorting allows for an easy transfer of information to the level II. Vertical lines on the level III separate the weeks and horizontal lines separate the master activities. The man-day estimate has been taken off the CAS sheets and penciled-in to the left of each activity number. The man-days have also been written   over   each   line   representing   the   activity duration. Where an activity was split between 2 weeks the  man-days  were  prorated  between  the  2  weeks. Master activity 10 has a total man-day estimate of 19 (the sum of the construction activity estimates). You can now transfer the information to a level II barchart. Figure  2-20  is  a  level  II  barchart.  The  master activities are listed in a column on the left and the weeks of the entire deployment across the top. The dates used are always the Monday of that week. Next to each master activity is the man-day estimate for that master activity. The next column is the weighted percent,  which  is  the  master  activity  man-day estimate divided by the total project man-day estimate Figure 2-20.—NCF level II barchart. 2-25

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing