Click Here to
Order this information in Print

Click Here to
Order this information on CD-ROM

Click Here to
Download this information in PDF Format

 

Click here to make tpub.com your Home Page

Page Title: Resource Leveling
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books

   

 

Back
Figure  2-14.—Network  calculation.
Up
Naval Construction Force/Seabee 1&C - Construction manual for building structures
Next
Figure 2-16.—Level III barchart sorted by early start date.

information  to  a  barchart.  Scheduled  dates  are  much easier to read on a barchart. Figure 2-16 is a level III barchart  sorted  by  early  start  date.  All  of  the construction activities are listed down the left-hand side. A time scale is at the top of the page. The time scale goes from the first workday of the project to the last workday. The start date, finish date, and duration of each construction activity is shown on the barchart. The  double  horizontal  dash  lines  represent  critical construction  activity  durations.  The  single  dash  lines represent noncritical activity durations. Free floats are shown as dots behind each noncritical activity. For activities with no free float you have to look at the activity that they are sharing floats with to find the total  float.  For  example,  the  total  float  for  activity 4000 is shown behind activity 4005. No free float on 4000  means  you  cannot  delay  it  without  delaying 4005 also. RESOURCE LEVELING Resource  leveling  involves  matching  the  construc- tion  activities  scheduled  to  the  crew  size  available.  You want the entire crew to be gainfully employed every day. You also want to keep up with the scheduled work Figure 2-15.—Logic relationships. and not fall behind. To perform resource leveling, you need a known crew size, a time-scaled schedule, and a histogram.  The  histogram  shows  how  many  people  in each rating are required on a daily basis to complete the tasks scheduled. You can create these documents by hand or computer. Figure 2-16 represents only the first page of a level III barchart. Look at figure 2-16 and you see can the resource histogram at the bottom of the page. The numbers give the required resources needed to complete the  critical activities scheduled for each day. These activities cannot be moved without delaying the project! The primary task in resource leveling is to schedule the noncritical work as you have people to do the work. In figure 2-17 the total float for noncritical activities has been penciled-in in the space between the activity numbers  and  descriptions.  The  crew  sizes  for  each noncritical  activity  also  have  been  penciled-in  next  to the activity start date. The total crew size in this example is 7. You have resource leveled this project for a small detachment scenario. Here the prime/sub arrangement is not practical and extensive cross-rate use of personnel is common. In  figure  2-18  notice  the  resource  leveling  process was started by committing to doing the critical path as shown and plugging in the resources. These resources can be figured by the computer or drawn in manually at  the  bottom  of  the  page.  The  critical  path  will obviously  not  keep  the  entire  crew  busy  (see  the original total resource numbers at the bottom of the page). The noncritical activities are shown on their early start dates, but you may need to delay the start dates if you lack the people to start the noncritical activities  at  that  time.  If  you  delay  the  start  of  a noncritical activity, you want to schedule its start as soon as you have people (available those days where total resources are less than 7). Figure  2-18  has  been  resource  leveled.  The activities  were  scheduled  beginning  with  the  least amount of total float to those with the most total float. Activity 2050 was scheduled first, then 2090, 3020, 3010,  4000,  4005,  4030,  and  4010.  This  process should be continued through the rest of the project. Notice  that  there  were  not  yet  any  personnel  to schedule  for  activities  2010,  2020,  2030,  7010,  or 7020. These resources would be carried over to the next page of the barchart. We also did not schedule activities 6020, 8080, 9010, or 8095. Even though they have the least amounts of total float, these activities have  early  starts  late  in  the  project  and  can  be rescheduled  later.  Remember  the  activities  are  shown by early start dates and can be moved forward only, 2-19

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing