Click Here to
Order this information in Print

Click Here to
Order this information on CD-ROM

Click Here to
Download this information in PDF Format

 

Click here to make tpub.com your Home Page

Page Title: Logic Nework
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books

   

 

Back
Figure 2-10.—Construction activity summary sheet (back).
Up
Naval Construction Force/Seabee 1&C - Construction manual for building structures
Next
Total Float

several  different  companies  is  required  to  ensure  that you  can  maintain  the  schedule.  Rough  level  II schedules  coordinate  the  planning  effort  between companies and ensure that no particular company or rating   is   overtasked   during   any   phase   of   the deployment.  Good  coordination  in  the  beginning  is less  painful  than  a  major  overhaul  later.  Having determined  the  sequence  and  approximate  duration  of each  master  activity,  you  can  construct  a  level  II barchart. Each project will have a level II. The 0ps officers  and  the  company  commanders  typically  track projects using a level II. Barcharts will be covered in greater  detail  later  in  this  chapter. LOGIC  NETWORK The logic network is the basic management tool for  control,  monitoring,  and  distribution  of  all resources that are directly related to time. The logic network at the planning stage is a pure dependency diagram. All activities are drawn in the order in which they   must   be   accomplished,   without   regard   to particular construction preference. One of the major uses of the logic network during the planning stage is to  indicate  all  activities  that  must  be  accomplished  to complete  a  particular  project  (fig.  2-11).  The individual network activities should be well-defined elements  of  work  within  the  project  and  should  be normally limited to a single rating. As a general rule, an  activity  should  be  created  for  any  function  that consumes  or  uses  direct  labor  resources.  Resources (manpower,  equipment,  tools,  or  materials)  MUST be tied  directly  to  the  CAS  sheet  and  network. The  crew  leader  constructs  a  logic  network showing the sequence of construction activities from the  first  to  the  last  and  the  dependencies  between activities. It is important to do the logic network when breaking  the  project  down  into  construction  activities to ensure no items of work are left out. You do not yet have construction activity durations, so you are only concerned  about  the  sequence  of  work.  Each construction  activity  is  represented  by  an  activity block. in the network shown in figure 2-11, activities 1020  and  1030  cannot  start  until  activity  1010  is finished.  Activity  1040  cannot  start  until  1020  is finished, and activity 1050 cannot start until 1030 and 1040 are finished. THE BASIC SCHEDULE (FORWARD AND BACKWARD  PASS) Using  the  crew  sizes,  you  can  now  determine construction activity durations. Go back to the logic diagram and insert the durations to determine the basic schedule. Practice with the example here and those included  later.  Some  minor  revisions  may  be  required to the basic schedule (see resource leveling) prior to setting  the  final  schedule.  On  the  precedence  network you  will  need  to  insert  into  an  activity  block  the activity number, description, and duration for each activity. A typical block is shown in figure 2-12. Figure 2-12.—Typical activity block. Figure 2-11.—Logic network. 2-15

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing