| |
Back Figure 2-10.—Construction activity summary sheet (back). | Up Naval Construction Force/Seabee 1&C - Construction manual for building structures | Next Total Float |
several different companies is required to ensure that
you can maintain the schedule. Rough level II
schedules coordinate the planning effort between
companies and ensure that no particular company or
rating is overtasked during any phase of the
deployment. Good coordination in the beginning is
less painful than a major overhaul later. Having
determined the sequence and approximate duration of
each master activity, you can construct a level II
barchart. Each project will have a level II. The 0ps
officers and the company commanders typically track
projects using a level II. Barcharts will be covered in
greater detail later in this chapter.
LOGIC NETWORK
The logic network is the basic management tool
for control, monitoring, and distribution of all
resources that are directly related to time. The logic
network at the planning stage is a pure dependency
diagram. All activities are drawn in the order in which
they must be accomplished, without regard to
particular construction preference. One of the major
uses of the logic network during the planning stage is
to indicate all activities that must be accomplished to
complete a particular project (fig. 2-11). The
individual network activities should be well-defined
elements of work within the project and should be
normally limited to a single rating. As a general rule,
an activity should be created for any function that
consumes or uses direct labor resources. Resources
(manpower, equipment, tools, or materials) MUST be
tied directly to the CAS sheet and network.
The crew leader constructs a logic network
showing the sequence of construction activities from
the first to the last and the dependencies between
activities. It is important to do the logic network when
breaking the project down into construction activities
to ensure no items of work are left out. You do not yet
have construction activity durations, so you are only
concerned about the sequence of work. Each
construction activity is represented by an activity
block. in the network shown in figure 2-11, activities
1020 and 1030 cannot start until activity 1010 is
finished. Activity 1040 cannot start until 1020 is
finished, and activity 1050 cannot start until 1030 and
1040 are finished.
THE BASIC SCHEDULE (FORWARD AND
BACKWARD PASS)
Using the crew sizes, you can now determine
construction activity durations. Go back to the logic
diagram and insert the durations to determine the basic
schedule. Practice with the example here and those
included later. Some minor revisions may be required
to the basic schedule (see resource leveling) prior to
setting the final schedule. On the precedence network
you will need to insert into an activity block the
activity number, description, and duration for each
activity. A typical block is shown in figure 2-12.
Figure 2-12.Typical activity block.
Figure 2-11.Logic network.
2-15
|