Back Figure 2-3.—Standard NCF project package outline. | Up Naval Construction Force/Seabee 1&C - Construction manual for building structures | Next Figure 2-5.—Project planning milestones. |
nine-folder project package. Figure 2-3 is an outline
of the standardized NCF project package. You will use
this format on all tasked projects. The forms for each
file may be obtained from the regimental operations
department. A flowchart showing the sequence of
planning steps is provided in figure 2-4. We will
examine the planning sequence and see how the
project package is created step by step. These steps
also are listed in the project planning milestones list
in figure 2-5. Planning milestones should be assigned
by Ops at the beginning of home port.
REVIEWING THE PLANS AND
SPECIFICATIONS
A thorough review of the plans and specifications
are absolutely necessary. Figure 2-6 provides a
checklist for this review. In addition to the checklist
items, many questions, such as those in the following
list, must be answered:
Scheduling
What is the scheduled progress at turnover?
Is sufficient time allotted?
Will long lead-time materials be available?
Is work required in occupied buildings?
Is roofing, sitework, or other weather-depen-
dent work to be done in the rainy season?
Do the specifications require phasing of work?
Site conditions
Are there any hazardous materials present (such
as asbestos floor tile, siding, roofing,
insulation)?
Figure 2-4.Project planning flowchart.