STANDARD NCF PROJECT PACKAGE OUTLINE
FILE #1 GENERAL INFORMATION FILE
FILE # 5 MATERIAL FILE
LEFT
Project Scope Sheet
LEFT
List of Long Lead Time Items
Tasking Letter
45-Day Material List
Project Planning Cheek List
Material Transfer Requests
Project Package Sign-Off Sheet
Add On/Reorder Justification Forms
Bill of Materials/Material Take-Off
RIGHT Project Organization
Comparison Worksheets
Deployment Calendar
Material Take-Off Worksheets
Preconstruction Conference Notes
Predeployment Visit Summary
RIGHT Bill of Materials (including all
Add-On/Reorder BMs)
FILE # 2 CORRESPONDENCE FILE
FILE # 6 QUALITY CONTROL FILE
LEFT
Outgoing messages and
correspondence
LEFT
Various Quality Contnrol Forms
Field Adjustment Requests (Design
RIGHT Incoming messages and
Change Directives)
correspondence
RIGHT Daily Quality Control Inspection
FILE # 3 ACTIVITY FILE
Reports
Quality Control Plan
LEFT
Constrution Activity Summary
Sheets of completed activities
FILE # 7 SAFETY/ENVIROMENT FILE
RIGHT Master Activity Summary
LEFT
Required Safety Equipment
Level II
Stand-Up Safety Lectures
Level II Precedence Diagram
Safety Reports Accident Reports
Master Activity Summary Sheets
Construction Activity Summary
RIGHT Safety Plan Highlighted EM 385
Sheets (Recommend Including filled
Environmental Plan (if applicable)
out 1250s and mineral products
requests.)
FILE # 8 PLANS FILE
FILE # 4 NETWORK FILE
LEFT
Site Layout
Shop Drawings
LEFT
Computer Printouts
Detailed Drawings (if required)
Level III Precedence Diagram
Rebar Bending Schedule
Form Material Worksheet
RIGHT Resource leveled plan for manpower
and equipment
RIGHT Project Plans
Equipment Requirement Summary
FILE # 9 SPECIFICATIONS FILE
LEFT
Technical Data
RIGHT Highlighted Specifications
Figure 2-3.Standard NCF project package outline.