Click Here to
Order this information in Print

Click Here to
Order this information on CD-ROM

Click Here to
Download this information in PDF Format

 

Click here to make tpub.com your Home Page

Page Title: Operations Department
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books

   

 

Back
Chapter 2 Project Planning and Management
Up
Naval Construction Force/Seabee 1&C - Construction manual for building structures
Next
Preliminary Deployment Planning

5. 6. Track  resources. As  the  crew  leader,  you  must  be  sure  the necessary  resources  are  available  on  the  project site on the day the work is to be performed. For materials  on  site,  this  will  be  as  easy  as submitting a material request, NAVSUP Form 1250-1, to the material liaison office (MLO) several  days  in  advance.  For  local  purchase requirements,  such  as  a  concrete  request  to MLO, a request may be required 2 to 3 weeks in advance. Control  resources. As the crew leader, you are also responsible for on-site  supervision  of  all  work  performed. Productive  employment  of  available  resourees to accomplish assigned tasking is your greatest challenge. OPERATIONS  DEPARTMENT An   understanding   of   the   operations   (Ops) organization and its responsibilities in the planning and  execution  of  construction  tasking  is  necessary before  any  further  discussion  of  project  management. You can refer to figure 2-1 for a clear picture of the organization. Operations Officer (S3) The  S3  has  functional  authority  over  the construction and disaster preparedness programs in the  battalion.  In  this  capacity  he  or  she  has  direct supervisory authority over the line companies. The S3 reports directly to the commanding officer. The S3 is responsible  for  the  assignment  of  all  construction Figure 2-1.—Operations department organization. resourees:  personnel,  equipment,  tools,  and  materials. Since  the  project  planning  process  involves  allocating these resources to specific projects, the S3 controls the project  planning  process,  oversees  each  planning phase,  and  approves  all  final  project  packages. Assistant Operations Officer (S3A) The   S3A   is   generally   responsible   for   the administrative/executive  efforts  and  record  keeping  of the Ops department. The S3A in case of his or her absence. Operations Chief (S3C) The   S3C   is   normally day-to-day   coordination   of acts for the Ops officer responsible   for   the personnel  within  the department  and  assists  them  in  carrying  out  their duties.  The  S3C  also  assists  crew  leaders  through  daily visits  to  the  jobsites  and  generally  assigns  E6  and below  OF-13  personnel  within  the  battalion. Engineering  Division The  engineering  division  provides  a  variety  of engineering  services  including  surveying,  concrete slump   and   strength   tests,   compaction   tests   and drafting.  Engineering  also  maintains  the  “as-built” drawings  for  projects  under  construction. Operations Administration In addition to typing operations reports such as situation reports (SITREPs), the Ops admin staff also provides   centralized   timekeeping   and   personnel distribution  status. Quality Control (QC) Division The QC division is staffed with a group of highly skilled  technicians  capable  of  instructing  personnel  to perform the work in the plans and specifications. These technicians are normally included in the planning and estimating  and  deployment  planning  groups.  They  have detailed knowledge of all facets of a project and are knowledgeable on the critical inspection items that must be followed for each network activity during each phase of  construction.  This  group  of  technical  experts,  as agents of the Ops officer, is the group within the battal- ion  most  capable  of  resolving  field  problems  with  the individual  construction  units. The QC division develops a QC plan intended to be  a  single-source  document.  This  document  outlines 2-2