Click Here to
Order this information in Print

Click Here to
Order this information on CD-ROM

Click Here to
Download this information in PDF Format

 

Click here to make tpub.com your Home Page

Page Title: Naval Facilities Engineering Command
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books

   

 

Back
Chapter 8 Contract Quality Assurance
Up
Naval Construction Force/Seabee 1&C - Construction manual for building structures
Next
Cognizant Authority

Maintain  a  log  of  all  correspondence  that  requires action. As contract work proceeds, monitor and properly document   significant   information,   such   as   the contractor’s   progress,   problems   experienced,   and pending  changes.     The  inspector’s  daily  report  is particularly  valuable  for  this  purpose.  Theese  reports form  the  historical  basis  of  the  position  of  the government  if  a  dispute  develops  between  the government and the contractor. Therefore, frequent visits to the contractor site and job status meetings are essential. Besides  constantly  reviewing  the  progress  of  a contract, you must make a constant effort to foresee problems the contractor might meet. One problem that has major influence on the contractor’s progress is late delivery   of   materials   and   equipment,   such   as air-handling  units  or  subcontractor  prefabricated  items. Furnishing  its  resources  and  expertise  to  help  the contractor  serves  the  best  interest  of  the  government. You  must  make  every  effort  to  relieve  this  kind  of problem instead of trying to justify or explain it. Many contract specifications are drawn up years ahead of the actual letting of a contract. Some items required   by   the   specifications   will   no   longer   be available and require replacement by similar items. This change requires initiating a change order. Change orders are formal changes to a basic contract and must meet  with  NAVFAC  instructions  and  result  from  one  or more  of  the  following  changes: l  Design l   Requirements l   Conditions l   Constructive Government  representatives  must  ensure  change orders do not needlessly delay the contractor’s progress. Additionally, they must assure all change orders get promptly   started,   negotiated,   and   issued   to   the contractor.  Any  delay  in  progress  by  a  contractor attributed to a change order must be of immediate concern to the government representatives. Take all possible actions to prevent delays that could result from change orders. Upon completion of a contract, both contractor and government  representatives  conduct  a  joint  final inspection. Document all discrepancies found during the  final  inspection.    Meeting  contract  specifications requires correction of these discrepancies. Upon the contractor’s completion of all contract requirements, the contractor executes release forms and submits the final invoice to the OIC. The NAVFAC P-68, Contracting Manual, guides the administration of contracts and is the primary guide for  all  Navy  representatives  of  the  government  on contracts. NAVAL FACILITIES ENGINEERING COMMAND In   the   administration   of   contracts,   the organizational chain of authority must be understood. NAVFAC  is  the  primary  contracting  authority  for  all construction  contracts,  facility  support  contracts,  and A/E contracts related to construction. NAVFAC is also responsible  for  providing  technical  and  managerial assistance. It also provides related engineering material and  equipment  to  Navy  and  Marine  Corps  shore facilities.   NAVFAC   is   also   responsible   for   all automotive, weight-handling (not material-handling equipment),  and  fire-fighting  equipment  assigned  to  the shore facilities of the Navy and Marine Corps. For a review  of  NAVFAC  responsibilities,  read  NAVFAC P-315. Major  Claimants Major  claimants,  such  as  CINCPACFLT  and CINCUSNAVEUR,  have  the  responsibility  for  the readiness of all their respective shore facilities. This includes the operations, maintenance, and repair of these  facilities.  NAVFAC  is  one  of  several  system commands  that  provide  logistical  support  to  these claimants.  NAVFAC  provides  support  by  assisting  with the  operation  and  maintenance  of  these  facilities. Engineering  Field  Divisions NAVFAC presently has five field divisions as its primary field organization. Officers in command of the engineering  field  divisions  (EFDs)  are  delegated contractual authority to award most NAVFAC contracts without prior approval.    The head of the contracts department is responsible for all contract functions except  those  involving  utilities  and  real  estate purchasing. Within  the  facilities  management department,  the  facilities  division  has  principal  interest in facilities maintenance management. This division 8-2

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing