Table 2-4.Production Efficiency Guide Factor Chart
MC = DL x WD x ME x AF
ME, and WD. The number of workdays is taken from
Use DL to represent the number of direct labor
the deployment calendar.
assigned, WD for the number of available workdays,
ME = WD - Lunch - Travel - Breaks-
Man-Day Equivalent (ME) is the number of man-days
expended (actual man-hours swinging hammers) in a
typical workday, and AF is the availability y factor.
Availability Factor takes into account that Seabees
assigned as direct labor are not available 100% of the
time. Multiply these four factors to figure the man-day
capability (MC). You can use this same equation to
determine the direct labor manning for a detail if you
substitute tasked man-days for MC and plug in AF,
Actual MHRS/work day
CONSTRUCTION ACTIVITY DURATIONS.
The man-day capability (MC) equation also can be
used to determine construction activity durations
expressed in the following equation:
Duration = MD estimated (CS x AF x ME)
or
Duration = MD estimated ÷ CS ÷ AF ÷ ME