| |
Back Activity Estimates | Up Builder Advanced - Construction manual for building structures | Next Table 2-4.—Production Efficiency Guide Factor Chart |
Construction Activities
As the crew leader, you must break the master
activities into construction activities. The work
element checklist, contained in appendix A in the
NAVFAC P-405 and the Seabee Crewleaders
Handbook, are an excellent reference for the
development of the construction activity list. A typical
Naval Mobile Construction Battalion (NMCB) project
might contain between 15 and 50 construction
activities. Construction activity numbers are usually
four digits. The first two digits identify the master
activity and the second two digits show a specific
construction activity within a master activity. The
number also includes a prefix assigned by OPS that
identifies the specific project. Looking at the list of
master activities example, this project could have a
construction activity for pre-fab forms numbered
0312. The number 03 represents master activity
concrete construction and the 1X distinguishes
concrete formwork and the 2 represents pre-fab
forms from the order of precedence in that master
activity. Refer to the Seabee Crewleaders Handbook
for the construction activities listing.
MAN-DAY ESTIMATES AND DURATIONS.
You need to know how to calculate man-days and
duration days for each construction activity. The
P-405 is the primary reference for Seabee man-day
estimates. The P-405 lists how many man-hours it
takes to do one unit of work. The size of the unit is
also given. The quantity of work is divided by the unit
size and multiplied by the man-hours required to do
one unit. You then divide by 8 man-hours per man-day
and multiply by a delay factor (DF). Tasking,
estimating, and reporting are always done in 8-hour
man-days, regardless of the length of the workday.
Note the following formula:
MDs = QTY Of WORK ÷ UNIT SIZE X MHRS
PER UNIT ÷ 8 x DF
For example, to install 16,000 sf of 1/2-inch
drywall over wall studs would require how many
man-days? The equation should be as follows:
MDs = 16,000 SF ÷ 1000 SF x 33 MHRS ÷ 8 = 66 x DF
PRODUCTION EFFICIENCY FACTORS.
Production efficiency factors are the first step in
adjusting man-day estimates based on your unique
circumstances. The intent of a production efficiency
factor is to adjust for factors that will make you more
or less productive than the average Seabee. In
calculating a production efficiency factor, consider
only those factors that affect the crew while on the job.
Table 2-4 lists eight production elements in the far-left
column. You need to consider the impact of each of
these production elements on each activity given a
specific crew, location, equipment condition, and so
on. Then assign a production factor between 25 (low
production) and 100 (high production) for each
element. A production factor of 67 is considered
average. Average these eight factors to figure your
production efficiency factor (PEF).
DELAY FACTORS. Before you can adjust the
man-day estimate, you must convert the production
efficiency factor to a delay factor according to the
graph shown in figure 2-14. You can find the delay
factor by dividing 67 (the average production factor)
by the production efficiency factor (DF = 67/63.6 =
1.05). (See table 2-4.) Using the delay factor of 1.05
you now can adjust the original man-day estimate as
shown in the following equation:
66 x 1.05 = 69.3 or 70 MD
This mathematical procedure has limitations. If,
for example, you were working outside in extremely
bad weather and all other factors were considered
average (weather = 25, all others = 67), you would
obtain a production efficiency factor of 62 and a delay
factor of 1.08. This 8 percent increase in the man-day
estimate would not adequately compensate for
working in extreme weather. You are not limited to the
method of delay factors in the P-405. Use common
sense when impacted by extreme circumstances.
Come up with what you feel is a reasonable delay
factor and discuss it with your chain of command. You
are not bound by either the delay factors or the
production rates in the P-405. To figure man-day
estimates, you can use your experience to determine
the logical production rates to use. Keep in mind that
the delay factor is only used to determine the man-day
estimate for a particular construction activity. Each
activity will have a different delay factor. All other
calculations use the availability factor.
AVAILABILITY FACTORS. Availability
factors take into account that Seabees assigned as
direct labor are not available 100 percent of the time.
Each Naval Construction Brigade provides the
availability y factors for planning purposes. Availability y
factors are sometimes still referred to as site efficiency
factors. These factors vary between 0.75 for main
body sites to 0.85 for detail sites. Using the following
equation, you can determine the man-day capability
(MC) for the main body and each detail.
2-27
|