| |
Back Estimating | Up Builder Advanced - Construction manual for building structures | Next Activity Estimates |
MATERIAL ESTIMATES
MATERIAL ESTIMATES consist of a listing and
description of the various materials and the quantities
required to construct a given project. Obtain the
information you will need to prepare material
estimates from the activity estimates, drawings, and
specifications. A material estimate is sometimes
referred to as a Bill of Material (BM) or a Material
Takeoff (MTO) sheet. (We will cover the BM and the
MTO a little later in this chapter.)
EQUIPMENT ESTIMATES
EQUIPMENT ESTIMATES are listings of the
various types of equipment, the amount of time, and
the number of pieces of equipment required for you to
construct a given project. Information, such as that
obtained from activity estimates, drawings,
specifications, and an inspection of the site, provides
the basis for preparing the equipment estimates.
LABOR ESTIMATES
The LABOR ESTIMATES consist of a listing of the
number of direct labor man-days required to complete
the various activities of a specific project. These
estimates may show only the man-days for each activity,
or they may be in sufficient detail to list the number of
man-days for each rating in each activityBuilder
(BU), Construction Electrician (CE), Equipment
Operator (EO), Steelworker (SW), and Utilitiesman
(UT). Man-day estimates are used for determining the
number of personnel and the ratings required on a
deployment. They also provide the basis for scheduling
labor in relation to construction progress.
When the Seabee Planners and Estimators
Handbook, NAVFAC P-405, is used, a man-day is a unit
of work performed by one person in one 8-hour day.
Battalions set their own schedules, as needed, to
complete their assigned tasks. In general, the work
schedule of the battalions based on an average of 55 hours
per person per week The duration of the workday is 10
hours per day, which starts and ends at the jobsite.
Direct labor includes all labor expended directly
on assigned construction tasks (either in the field or in
the shop) that contributes directly to the completion of
the end product. Direct labor must be reported
separately for each assigned construction item. In
addition to direct labor, the estimator must also consider
indirect labor and readiness and training. Indirect labor
includes labor required to support construction operations
but does not, in itself, produce an end product. Refer to
the
COMSECONDNCB/COMTHIRDNCBINST
5312.1 for more information on labor.
ESTIMATOR
An ESTIMATOR is a person who evaluates the
requirements of a task. A construction estimator must
be able to picture the separate operations of the job
mentally, as the work progresses through the various
stages of construction and be able to read and obtain
accurate measurements from drawings. The estimator
must have an understanding of math, previous
construction experience, and a working knowledge of
all branches of construction. The estimator must use
good judgment to determine what effect numerous
factors and conditions have on project construction
and what allowances should be made for each of them.
The estimator must be able to do careful and accurate
work. A Seabee estimator must have ready access to
information about the material, equipment, and labor
required to perform various types of work under
conditions encountered in Seabee deployments. The
collection of such information on construction
performance is part of estimating. Since this kind of
reference information may change from time to time,
the estimator should review it frequently.
The tables and diagrams in the Seabee Planner 3
and Estimators Handbook, NAVFAC P-405, will save
you time in preparing estimates, and when understood
and used properly, provide you with accurate results.
Whenever possible, the tables and the diagrams used
were based on Seabee experience. Where suitable
information was not available, construction
experience was adjusted to represent production under
the range of conditions encountered in Seabee
construction. A thorough knowledge of the project
drawings and specifications makes you alert to the
various areas in which errors may occur.
Need for Accuracy
QUANTITY ESTIMATES are the basis for
purchasing materials, determining equipment, and
determining manpower requirements. They are also
the basis for scheduling in terms of material deliveries,
equipment, and manpower. Accuracy in preparing
quantity estimates is extremely important since these
estimates have widespread uses, and errors can be
multiplied many times. Say, for example, a concrete
slab is to measure 100 feet by 800 feet. If you misread
the dimension for the 800-foot side as 300 feet, the
computed area of the slab will be 30,000 square feet,
when it should actually be 80,000 square feet. Since
area is the basis for ordering materials, there will be
2-25
|