| |
Back Figure 2-12.—Redicheck plan and specification review. | Up Builder Advanced - Construction manual for building structures | Next Project Planning, Continued |
Modifications to previous projects
Work sheets from previous projects
Work element checklist (NAVFAC P-405)
Project turnover files
NCBs/NCRs
There are no specific definitions as to what
constitutes an activity, and it is largely a matter of
individual interpretation according to the
requirements of a particular project. A good rule is,
DO NOT plan a project in any more detail than is
necessary to manage the scheduling of the work
properly. For most NCF projects, construction
activities should not be less than 1 day in duration
(preferably not less than 3 days). Refer to the
Planners and Estimators Handbook, NAVFAC
P-405 and the Seabee Crewleaders Handbook for
more information on network analysis.
PROJECT PLANNING
Two basic ground rules are involved in analyzing
a project. First, planning and scheduling are separate
operations. Second, planning must always precede
scheduling. If you do not plan sequentially, you will
end up with steps out of sequence which may delay the
project substantially. Each NCF project from the
initial planning phase through the execution phase to
the closeout phase is documented in a standard
five-section package. This section focuses on the
planning phase of a project.
The project folder, or package, consists of five
individual project files. These files represent not only
the project in a paper format but they also give you, as
the project crew leader, project manager, or crew
member, exposure to the fundamentals of construction
management. This package will be presented to OPS
in phases; refer to the Seabee Crewleaders Handbook
for more information pertaining to project
management.
Listed below are the instructions needed to
complete a typical NCF project package. The forms
marked with an asterisk are mandatory on all
projects. Small projects of short duration or ABFC
projects may require only the mandatory forms. Other
forms are used as needed. Forms may be computer
generated but must be the same content as shown.
A. NCF Project Package Contents: To be placed
at the beginning of the project package 3-ring binder.
B. Section #1 - General Information and
Correspondence.
1.
2.
1A Cover Sheet: Recommend using tabbed
dividers for all section cover sheets.
a. *Tasking Letter/Correspondence:
Distributed by S3 early in home port.
b. *Outgoing Messages and Correspondence:
File in chronological order, oldest on bottom
to newest on top.
c. *Incoming Messages and Correspondence:
File in chronological order, oldest on bottom
to newest on top.
1B Cover Sheet
a. Project Scope Sheet
b. Project Organization: In addition to this,
include a compete list of all prime and sub
personnel assigned to the project.
c. Project Planning Milestones: This list
can be added to if necessary. Ops should be
contacted when assigning dates.
d. Project Package Sign-Off Sheet: To be
signed off prior to the RDE.
Deployment Calendar
Preconstruction Conference Summary
Predeployment Site Visit Summary
Joint Turnover Memorandum: This
e.
f.
g.
h.
will be completed jointly by personnel from
both battalions for turnover projects.
i. Pre-BOD Inspection Request: This
will be completed by the crew leader two
working days prior to the requested date of
inspection.
C. Section #2 Activities and Network
1. 2A Cover Sheet
a *Level II Bar Chart: Particular care
should be taken in man-day totals recorded on
this form. All numbers will match Level III
calculations. Horizontal and vertical totals
will match exactly.
b. *Two Week Schedule: This will be
completed each week by the crew leader. The
Company will present it to Ops at the weekly
Ops meeting. The crew leader will brief the
crew on this and post on the jobsite.
2-21
|