| |
Back Project Specfications | Up Builder Advanced - Construction manual for building structures | Next Figure 2-12.—Redicheck plan and specification review. |
15. Mechanical Systems include plumbing,
heating, air conditioning, fire-protection systems, and
refrigeration systems.
16. Electrical Systems include electrical service
and distribution systems, electrical power equipment,
electric heating and cooling systems, lighting, and other
electrical items.
Each of the previous divisions is further divided
into sections. You can find information on the required
sections of Division 1 in the MIL-HDBK-1006/1,
Policy and Procedures for Project Drawing and
Specification Preparation. The Division 1 section is
generally common to all projects done under a
construction contract. Divisions 2 through 16 contain
the technical sections that pertain to the specific
project for which the spec writer has prepared the
specification. These technical sections follow the
CSI-recommended three-part section format. The first
part, General, includes requirements of a general
nature. Part 2, Products, addresses the products or
quality of materials and equipment to be included in
the work. The third part, Execution, provides detailed
requirements for performance of the work.
Some construction industries have developed a
division 17 or 18 to the CSI due to the changing
technology of construction. Even NAVFAC has
developed a division 17, called the Expeditionary
Structures, which includes K-SPAN and High
Tension Fabric buildings. Refer to chapter 9 for more
information on Division 17 or the P-405.
GUIDANCE
Usually, the engineer or spec writer prepares each
section of a specification based on the appropriate
guide specification listed in the Engineering and
Design Criteria for Navy Facilities, MIL-BUL-34.
This military bulletin (issued quarterly by the Naval
Construction Battalion Center, Port Hueneme,
California) lists current NAVFACENGCOM guide
specifications, standard specifications and drawings,
definitive drawings, NAVFAC design manuals, and
military handbooks that are used as design criteria.
The preceding material provides only a brief
overview of construction specifications. For
additional guidance regarding specification
preparation, refer to Policy and Procedures for Project
D r a w i n g a n d S p e c i f i c a t i o n P r e p a r a t i o n ,
MIL-HDBK-1006/1, and EA Intermediate/Advanced.
PLANNING
PLANNING is the process the Builders use to
determine requirements and to devise and develop
methods and actions for constructing a project. Good
construction planning is a combination of the
following elements: understanding the plans and
specifications and understanding and analyzing the
available resources, such as material, equipment, and
manpower. PLANNING is also the process of
determining the working environment, quality control,
and safety procedures/precautions. All of these
elements depend upon each other and must be
considered in any well-planned project.
In the late 1950s, a new system of project
planning, scheduling, and control came into
widespread use in the construction industry. The
critical path analysis (CPA), critical path method
(CPM), and project evaluation and review technique
(PERT) are three examples of about 50 different
approaches. The basis for each of these approaches is
the analysis of a network of events and activities. The
generic title of the various networks is network
analysis.
NETWORK ANALYSIS
The NETWORK ANALYSIS approach is now the
accepted method of construction planning in many
organizations. Network analysis forms the core of
project planning and control systems. Network
analysis separates the planning of the sequence of jobs
from the scheduling of times for the jobs, thus
overcoming simultaneous, and less effective, planning
and scheduling.
All projects consist of separate but interrelated
operations. In network analysis, these interrelated
operations are called activities. Activities are
broken down into two phases: master activities (Level
IIs) and construction or detailed activities (Level IIIs).
Master and construction activities will be covered
throughout this section.
The first stage in applying this technique is the
preparation of a list of all activities that constitute the
project to be scheduled. This list can be obtained in the
following ways:
Study of the plans and the specifications (fig.
2-1 2)
Study of the manufacturers specifications
Bill of materials (BMs)
2-19
|