| |
Back Chapter 3 Concrete Construction | Up Builder Advanced - Construction manual for building structures | Next Wall Form Design |
Raising of large form panels should not be
attempted in heavy gusts of wind, neither by hand nor
by crane.
Skip loader cables and brakes must be inspected
frequently to prevent injuries caused by falling skips.
The mixer operator must never lower the skip
without first ensuring there is no one under it.
The area around the mixer must be kept clear.
Dust protection equipment must be issued to crew
members engaged in handling cement, and they must
wear the equipment when so engaged. Workers should
stand with their backs to the wind, whenever possible,
to prevent cement and sand from being blown into their
eyes and faces.
Whenever the mixer drum is being cleaned, the
switches must be open, the throttles closed, and the
control mechanism locked in the OFF position.
Whenever possible, a flagman or watchman
should be stationed near the mixer to warn all hands
when a batch truck is backing up to the skip. The
watchman should use a whistle to warn any personnel
in the danger zone. DANGER-KEEP AWAY signs
should be placed where they can readily be seen.
FORMWORK
FORMWORK is a temporary structure that
supports its own weight and that of the freshly placed
concrete as well as the live loads imposed upon it by
materials, equipment, and workmen. As a Builder
serving in the capacity of a form designer or as the
supervisor of a form building crew, you should take
into account the three principle objectives when using
formworkeconomy, quality, and safety.
Economy is the major concern since formwork
may represent as much as one third of the total cost of
a concrete structure. Savings depend on the ingenuity
and experience of the formwork designer or
supervisor. Judgment in the selection of materials and
equipment, in planning fabrication and erection
procedures, and in scheduling reuse of forms will
expedite the job and help reduce formwork costs. In
designing and building formwork, you should aim for
maximum economy without sacrificing quality or
safety. Shortcuts in design or construction that
endanger quality or safety may be false economy. For
example, if the forms do not produce the specified
surface finish, much hand rubbing of the concrete may
be required; or if forms deflect excessively, bulges in
the concrete may require expensive chipping and
grinding. Obviously, economy measures that lead to
formwork failure also defeat their own purpose. The
most commonly used form materials are earth, metal,
lumber, plywood, and fiber.
FORM DESIGN
Forms must be designed for all the weight to which
they are liable to be subjected, including the dead load
of the forms, the plastic concrete in the forms, the
weight of crew members, the weight of equipment and
materials that may be transferred to the forms, and the
impact due to vibration. These factors vary with each
project, but none should be neglected. Ease of erection
and removal are also important factors in the
economical design of forms. Platforms and ramp
structures independent of formwork are sometimes
preferred to avoid displacement of forms due to
loading and impact shock from crew members and
equipment. Formwork for concrete must support all
vertical and lateral loads that may be applied until
these loads can be carried by the concrete structure
itself. Loads on the forms include the weight of
reinforcing steel and fresh concrete, the weight of the
forms themselves, and various live loads imposed
during the construction process. Consideration must
be given to such conditions as unsymmetrical
placement of concrete, uplift, and concentrated loads
produced by storing supplies on the freshly placed
slab. Rarely will there be precise information as to the
loads the formwork maybe subjected to; therefore, the
architect or Builder must make some safe assumptions
that will hold good for conditions generally
encountered.
Vertical Loads
Vertical loads on formwork include the weight of
reinforced concrete together with the weight of the
forms themselves, which are regarded as dead loads,
and the live loads imposed by the crew members and
the equipment used during construction. The majority
of all formwork involves concrete weighing 150
pounds per cubic foot. Minor variations in this weight
are not significant, and in most cases, 150 pounds per
cubic foot, including the weight of the reinforcing
steel, is commonly assumed for design. Formwork
weights vary from as little as 3 or 4 pounds per square
foot (psf) to 10 to 15 pounds per square foot. When the
frame work weight is small in relation to the weight of
the concrete plus the live load, it is frequently
neglected. If concrete weighs 150 pounds per cubic
foot, it will place a load on the forms of 12.5 pounds
per square foot for each inch of slab thickness. Thus a
3-2
|