Click Here to
Order this information in Print

Click Here to
Order this information on CD-ROM

Click Here to
Download this information in PDF Format

 

Click here to make tpub.com your Home Page

Page Title: Planning Documentation
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books

   

 

Back
Manpower Estimates
Up
Builder 3&2 Volume 01 - Construction manual for building structures
Next
Project Folder

for  completion.    Material schedules show when the material is needed on the job. They may also show the  sequence  in  which  materials  should  be  delivered. Equipment  schedules  coordinate  all  the  equipment  to be used on a project. They also show when it is to be used  and  the  amount  of  time  each  piece  of  equipment is  required  to  perform  the  work.  Manpower  schedules coordinate the manpower requirements of a project and show the number of personnel required for each activity.  In  addition,  the  number  of  personnel  of  each rating  (Builder,  Construction  Electrician,  Equipment Operator,  Steelworker,  and  Utilitiesman)  required  for each activity for each period of time may be shown. The time unit shown in a schedule should be some convenient interval, such as a day, a week, or a month. NETWORK  ANALYSIS Network  analysis  is  a  method  of  planning  and c o n t r o l l i n g    p r o j e c t s    b y    r e c o r d i n g    t h e i r interdependence in diagram form. This enables you to undertake each problem separately. The diagram form, known as a network diagram, is drawn so that each job is represented by an activity on the diagram, as shown in figure 9-1.    The direction in which the activities  are  linked  indicates  the  dependencies  of  the jobs  on  each  other. PROGRESS CONTROL Progress  control  is  the  comparing  of  actual progress   with   scheduled   progress   and   the   steps necessary   to   correct   deficiencies   or   to   balance activities  to  meet  overall  objectives. PLANNING DOCUMENTATION LEARNING  OBJECTIVE:  Upon  completing this  section,  you  should  be  able  to  give  the documentation  requirements  necessary  in planning a construction project. There are two basic ground rules in analyzing a project. First, planning and scheduling are separate operations.  Second,  planning  must  always  precede scheduling.  If  you  don’t  plan  sequentially,  you  will end  up  with  steps  out  of  sequence  and  may substantially delay the project. Everyone concerned should  know  precisely  the  following  aspects  of  a project: What it is; Its start and finish points; Its external factors, such as the schedule dates and requirements of other trade groups; Figure 9-1 .—Planning and estimating a precedence diagram. 9-3

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing