| |
Back Chapter 9 Planning, Estimating, and Scheduling | Up Builder 3&2 Volume 01 - Construction manual for building structures | Next Planning Documentation |
schedules, errors in these estimates can multiply
many times. Be careful in their preparation!
MATERIAL ESTIMATES
A material estimate consists of a listing and
description of the various materials and the quantities
required to construct a given project. Information for
preparing material estimates is obtained from the
activity estimates, drawings, and specifications. A
material estimate is sometimes referred to as a Bill of
Material (BM) or a Material Takeoff (MTO)
Sheet. (We will discuss the BM and the MTO a little
later in the chapter.)
EQUIPMENT ESTIMATES
Equipment estimates are listings of the various
types of equipment, the amount of time, and the
number of pieces of equipment required to construct a
given project. Information, such as that obtained
from activity estimates, drawings, specifications, and
an inspection of the site, provides the basis for
preparing the equipment estimates.
MANPOWER ESTIMATES
The manpower estimate consists of a listing of the
number of direct labor man-days required to complete
the various activities of a specific project. These
estimates may show only the man-days for each
activity, or they may be in sufficient detail to list the
number of man-days for each rating in each
activityBuilder (BU), Construction Electrician
(CE), Equipment Operator (EO), Steelworker (SW),
and Utilitiesman (UT). Man-day estimates are used
in determining the number of personnel and the
ratings required on a deployment. They also provide
the basis for scheduling manpower in relation to
construction progress.
When the Seabee Planners and Estimators
Handbook, NAVFAC P-405, is used, a man-day is a
unit of work performed by one person in one 8-hour
day or its equivalent. One man-day is equivalent to a
10-hour day when the Facilities Planning Guide,
NAVFAC P-437, is used.
Battalions set their own schedules, as needed, to
complete their assigned tasks. In general, the work
schedule of the battalion is based on an average of 55
hours per man per week. The duration of the workday
is 10 hours per day, which starts and ends at the
jobsite. This includes 9 hours for direct labor and 1
hour for lunch.
Direct labor includes all labor expended directly
on assigned construction tasks, either in the field or in
the shop, that contributes directly to the completion of
the end product.
Direct labor must be reported
separately for each assigned construction item. In
addition to direct labor, the estimator must also
consider overhead labor and indirect labor. Overhead
labor is considered productive labor that does not
contribute directly or indirectly to the product. It
includes all labor that must be performed regardless
of the assigned mission. Indirect labor includes labor
required to support construction operations but does
not, in itself, produce an end product.
ESTIMATOR
An estimator is a person who evaluates the
requirements of a task. A construction estimator must
be able to mentally picture the separate operations of
the job as the work progresses through the various
stages of construction and be able to read and obtain
accurate measurements from drawings.
The
estimator must have an understanding of math,
previous construction experience, and a working
knowledge of all branches of construction. The
estimator must use good judgment when determining
what effect numerous factors and conditions have on
construction of the project and what allowances
should be made for each of them. The estimator must
be able to do careful and accurate work. A Seabee
estimator must have ready access to information
about the material, equipment, and labor required to
perform various types of work under conditions
encountered in Seabee deployments. The collection
of such information on construction performance is
part of estimating.
Since this kind of reference
information may change from time to time,
information should be frequently reviewed.
SCHEDULING
Scheduling is the process of determining when an
action must be taken and when material, equipment,
and manpower are required. There are four basic
types of schedules: progress, material, equipment,
and manpower.
Progress schedules coordinate all the projects of a
Seabee deployment or all the activities of a single
project. They show the sequence, the starting time,
the performance time required, and the time required
9-2
|