Click Here to
Order this information in Print

Click Here to
Order this information on CD-ROM

Click Here to
Download this information in PDF Format

 

Click here to make tpub.com your Home Page

Page Title: Figure 4-15.—Transformer size calculations.
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books

   

 

Back
Figure 4-13.—Polarity markings and directions of voltages when polarity is subtractive.
Up
Construction Electrician Intermediate - Electricity handbook for electricians
Next
Table  4-1.—Demand  Factor

strength  of  the  pole  or  the  crossarms  and  bolts as the barracks, is noted. Lines representing the service supporting  them. leads are drawn between the pole and the building. 2.   When  more  than  one  transformer  is  installed  on crossarms, the weight should be distributed equally on the two sides of the pole. 3.  Single-phase  distribution  transformers  of  100 kVA or smaller are usually placed above the secondary mains if conditions permit. Those larger than 100 kVA are usually platform or pad mounted. Your next step is to determine the total connected load of each service. It sounds complicated, but what it actually amounts to is summing up the power required by the lights and motors in each barracks. This power demand is noted in each square representing a barrack (fig. 4-15). 4.   Lightning arresters and fused cutouts have to be installed  on  the  primary  side  of  all  distribution transformers except the self-protected type. Next, figure out the kVA load per pole. In this particular example, each pole services two barracks; therefore, the kVA load of a pole will be the sum of the total connected loads of the two barracks served by that pole. 5. Ground wires are required to be covered with plastic or wood molding to a point 8 feet above the base of the pole. What  is  involved  in  the  determination  of  the transformer size? Let’s suppose you are given the job of  installing  a  single-phase  transformer  in  a  certain area of the base. This area contains 10 barracks that receive power from a 2,400-volt overhead primary main. The electrical equipment in the barracks consists of single-phase lights or motors operating at either 110  or  220  volts.  A  three-wire  overhead  secondary main distributes the secondary voltage alongside the barracks.  Service  leads  complete  the  connection between the secondary main and each building. Now, calculate the total maximum connected load on the transformer. As you can see from figure 4-15, the total connected load is the sum of the kVA loads per pole. It amounts to 35.05 kVA. This amount of 35.05 kVA   represents   the   amount   of   power   that   the transformer would have to supply if all the lights and motors  were  consuming  power  at  the  same  time. Although that possibility exists, the time interval would be small compared to the length of time that only a portion of the total load would be on. Therefore, it is necessary to calculate only the maximum demand load and then use this figure as a basis for determining transformer  size. The first thing you should do is make a rough drawing of the area. When you are finished, it should look like figure 4-15. The location of each pole, as well An approximation of the maximum demand load can be computed by multiplying the total maximum connected load by the demand factor listed in table 4-1. In this example, the maximum demand is 35.05 times Figure 4-15.—Transformer size calculations. 4-11

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing