PROJECT QC PLAN
I. Project Number and Title:
II. Project Location:
III. Prime Contractor:
Subcontractor: (a)
(b)
IV. Project Scope:
V. Types of Testing Required (soil. concrete, etc. ):
VI.
Types of Associated Risk (fire, fumes, noise, etc.):
VII Special Training Requirements:
VIII. Special License Required:
IX.
Engineering Controls (guard rails, welding curtains, etc.):
X.
Testing Equipment Required (state how it is to be used):
Xl.
Personal Protective Equipment Required for Testing:
Project Planner.
Print name, rate, and company/det
QC Chief:
Approved/Disapproved
Signature
Reason for disapproval:
CEIF0113
Figure 1-13.Project QC plan.