Back Table 1-4.—Seabee Project Package | Up Construction Electrician Intermediate - Electricity handbook for electricians | Next Network Analysis |
Table 1-4.Seabee Project PackageContinued
SECTION #4 PLANS
4A
*Quality Control Plan Cover Sheet
*Quality Control Plan
*Safety Plan Cover Sheet
*General Safety Plan
*Safety Plan
*Environmental Plan
4B
Daily Quality Control Inspection Reports
Field Adjustment Request (FAR) Submittal Log
FARs
Request For Information (RFI) Submittal Log
RFIs
Design Change Directive (DCD)
Concrete Placement Clearance Forms
Pre-placement Photos for Concrete Placements
Asphalt Pavement Clearance Forms
Utility Interruption Request
Excavation Request
Road Closure Request
Engineering Service Request
Minerals Products Request
Other QC Forms
Daily Safety Inspection Reports
Emergency Phone Numbers
Navy Employee Report of Unsafe or Unhealthful Working Conditions
Required Safety Equipment
Daily Safety Lecture Log
Accident/Near Mishap/Mishap Reports
Highlighted 29 CFR 1926
Hazardous Materials Inventory Sheet
Other Safety Forms
SECTION #5 DRAWINGS/SPECIFICATIONS
5A
*Project Plans
**Highlighted Specifications
5B
Site Layout
Shop Drawings
Detailed Slab Layout Drawings
Forming Plans
Rebar Bending Schedule
Other Sketches/Drawings
Technical Data
1-11
|