Back Overcurrent Protection | Up Construction Electrician Basic - Electricity handbook for electricians | Next Generator Watch |
figure 3-13. Load cables can be plugged into the
receptacles along the front (fig. 3-13, view A). With the
cover raised (fig. 3-13, view B), access to the circuit
breakers and test jacks is provided. This panelboard is
an advanced-base distribution center. A single-line
Portable generators and panelboards can be placed
into service quickly and with relatively little effort,
compared to a permanent installation.
Do not let
expedience cause you to become careless, though, in
placing the equipment and routing the load cables.
Careful planning can result in a much safer and more
diagram of the bus and circuit breakers is shown in
efficient installation for both you and your fellow
figure 3-14.
Seabees.
Figure 3-13.Portable power distribution panelboard.
3-16
|