TM  55-1520-240-23-9 11-6.3 ISOLATION  PROCEDURES FOR CHECKING CONTROLS LOOSENESS (Continued) 11-6.3 50. Working  through  right  landing  light access  (69), check  six  connecting  links  (70  thru  75) for loose swaged  inserts  (Tasks  11-7  and  11-7.1)  and loose  rod  end  bearings  (Task 11-9). 51. Check link (76) for  loose  bearing  (Task 11-9). 52. Working  through  left  landing  light  access  (77), check  eight  connecting  links  (78  thru  85)  for loose  swaged  inserts (Tasks  11-7  and  11-7.1) and  loose  rod  end  bearings (Task  11-9). 53. Check link (86) for  loose  bearing  (Task 11-9). 11-34