Charging Batteries:
Up
TM-9-6140-200-14 Lead-Acid Storage Batteries Manual
Next
Charging Batteries - continued



TM 9-6140-200-14
(6) Adjust charging amperage. Use the ammeter charging rate control knob to
adjust ammeter amperage as near as possible to 5 amperes for each battery
on charge ( Figure 3-21).
Figure 3-21
(a) Check the cables on each battery showing low voltage. Check the
location where the cable goes into the charger.
(b) If any cable plug-in does not make connection to a receptacle, try
interchanging cables at the charger. It this is not successful with any
given cable connection, charger is defective. Turn in charger.
(7) Use the following as a guide to recharge 12 volt lead-acid military batteries.
a. Pretest Battery (ies).
(1) Check all batteries for voltages and/or specific gravity readings. Use
the hand held tester (Item 20, Appx. B) to check for voltage and Load
testing and/or use the Optical (Item 21, Appx. B) or hydrometer
(Item 19, Appx. B) for specific gravity readings.
(2) For open circuit voltage (OCV) you may also use a multi-meter
(Item 12, Appx. B).
(3) Group batteries for charging as follows.
3-30