Table 3-5. Performance Test Procedures
Up
TM-11-6130-392-34 Charger Battery PP-7286/U Manual
Next
Figure 3-12. Battery Charging Tray Assembly Wiring Diagram.



TM 11-6130-392-34
c.  Insert the two wires of replacement cable
c. Installation procedures are essentially the reverse
assembly through the two holes in cable bushing.
of removal procedures (fig. 3-12).
d. Solder black wire to terminal 3 of SW1 and white
3-23. Switch
wire to E1 (fig. 3-12).
Removal and installation of any switch (2, fig. 2-1.1) is
3-26. Cable Bushing
as follows:
Removal and installation of cable bushing (8, fig. 2-1.1)
a. Note and record the switch terminals from which
is as follows:
the wiring is to be removed, then unsolder the wiring
from rear of switch.
Remove cable assembly (refer to para 3-25).
a.
b. Unscrew the hex nut from rear of switch and
b. Using an arbor press, press cable bushing from
remove switch.
battery holder (11, fig. 2-1.1).
c. Installation procedures are essentially the reverse
c. Using an arbor press, press replacement cable
of removal procedures (fig. 3-12).
bushing into battery holder.
3-24. Banana Plugs
d. Install cable assembly (refer to para 3-25).
Removal and installation of either banana plug (4 and 5,
3-27. Threaded Insert
fig. 2-1.1) is as follows:
Removal and installation of threaded insert (10, fig.
a. Remove insulation sleeving (6, fig. 2-1.1).
2-1.1) is as follows:
b. Unscrew shell from plug and unsolder wire.
a. Turn cover (3, fig. 2-1.1) upside down and, using
an arbor press, press threaded insert from cover.
c. Slip new insulation sleeving over wire and
resolder wire to replacement plug.
b. Turn cover rightside up and, using an arbor
press, press replacement threaded insert into cover.
d.
Screw shell onto plug.
3-28. Electrical Wire
e.  Slide insulation sleeving over shell and shrink into
place with heat gun.
Removal and installation of electrical wire is as follows:
3-25.
Cable Assembly
a. Unsolder the defective wire from its connecting
terminals.
Removal and installation of cable assembly (7, fig.
2-1.1) is as follows:
b. Solder the replacement wire to its proper
terminals (fig. 3-12).
a. Unsolder white wire from E1 (fig. 3-12) and black
wire from terminal 3 of SW1 (fig. 3-12).
b. Pull the two wires of cable assembly from cable
bushing (8, fig. 2-1.1).
Change 1 3-23