![]() ![]() TM 32-5985-342-14&P
The following cautions appear in the text of this manual and are repeated here for emphasis.
CAUTION
Float a fine grain surface on the top of the piers. Allow a minimum of 28 days for the concrete to
cure before erection of tower. (Page 24)
CAUTION
While tensioning cable braces, during installation, keep tower legs plumb and straight to prevent
unwanted deflection and prestressing of leg members. (Page 2-7)
CAUTION
Before the AS-2304/G antenna is raised, position the carriage so the 7/16-inch-diameter holes of
horizontal brace No. 2 are aligned with those of the carriage. Interference may occur between
antenna elements and tower if carriage is not aligned with horizontal brace. (Page 3-6)
CAUTION
Before the AN/GSA-131(V)l antenna is raised, align the 7/16-inch-diameter holes of horizontal
brace No. 1. With those of the carriage and secure with hardware provided. Damage to
equipment may occur if the carriage is improperly positioned too far away from tower. (Page 3-6)