Page Title: Figure 2-6. 80-Foot Tower Erection, Sheet 13 of 18
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 

Back
Figure 2-6. 80-Foot Tower Erection, Sheet 12 of 18
Up
TM-32-5985-200-15 Antenna System QRC-280 (A) Manual
Next
Figure 2-6. 80-Foot Tower Erection, Sheet 14 of 18

CE- 1008
A. When first guy level is reached, install two horizontal cable braces on the tower just below guy level (see
detail D on figure 2-4).
B. Determine the location of the guy anchor as shown on figure 2-4, sheet 2.
C. With the digging bar or a shovel, dig a pilot hole about 6" deep x 12" dia to aid in starting the anchor.
D. Screw anchor into the ground at a 45-degree angle until the top of the eye is not more than 4" above the
ground surface.
E. Attach guy winch to the anchor with clevis or guy spacer (figure 2-4, sheet 5).
F. Pass the slack end of the guy through the snubbing slot of the winch.
G. Leave enough slack in the guy cable to allow at least 1-1/2 turns to be wound on the winch before tensioning
guy.
H. Do not place the guy under too much tension until all four guys of a given set are attached to their winches.
I.  Guys should be tensioned simultaneously while checking the tower for plumb.
J.  Use the tensiometer as shown in figure 2-6, sheet 14, and tension each guy to 800 lbs. The locking pin must
be installed in the guy winch after each takeup.
K. When proper tension has been reached, continue erecting tower as shown on sheet 12.
Figure 2-6. 80-Foot Tower Erection, Sheet 13 of 18
2-33