![]() ![]() TM 11-5985-362-13
·
Stand at the TOWER BASE and by sighting determine new direction of radiation (beam).
·
Hold CENTER LAYOUT WIRE at SLEEVE with marker tag 5 on arrowhead of TOWER BASE.
·
Rotate the front end of CENTER LAYOUT WIRE (hold at SLEEVE with marker tag 1) to new direction of
radiation (beam).
·
Rotate back of CENTER LAYOUT WIRE (hold at SLEEVE with marker 6) so wire is again in a straight line.
·
Install new 66 inch ANCHORS at CENTER LAYOUT WIRE SLEEVES with marker tags 1 and 6. (Refer to
WIRE to SLEEVE with marker tag 5 on the CENTER LAYOUT WIRE (at TOWER BASE).
·
Holding SLEEVES with marker tags 4 and 5 together at the TOWER BASE, stretch out the BACK LAYOUT
WIRE so that it is 900 to the CENTER LAYOUT WIRE.
2-51
|
|